The Seventh Circuit upheld a dredge and fill permit issued by the U.S. Army Corps of Engineers for a highway project that crosses wetlands in Indiana. The Corps adequately considered practicable…
The Tenth Circuit upheld a U.S. Army Corps of Engineers dredge and fill permit allowing a railroad company to build a terminal on land outside Kansas City, Kansas, that contains streams and…
A district court upheld the U.S. Army Corps of Engineers' decision to issue a CWA §404 permit to a mining company for the construction of a valley fill and sediment pond in conjunction with…
The Fourth Circuit held that the U.S. Army Corps of Engineer violated NEPA when it issued a CWA §404 permit allowing a developer to build a mooring facility and boat ramp 3,000 feet from the…
The D.C. Circuit held that the U.S. Army Corps of Engineers complied with the CWA when it issued a permit authorizing the discharge of dredge and fill material into wetlands outside Tampa, Florida…
The Eleventh Circuit vacated a lower court decision remanding a permit issued by the U.S. Army Corps of Engineers back to the agency and enjoining a mining company from conducting operations…
The court holds that the U.S. Army Corps of Engineers did not violate the National Environmental Policy Act (NEPA) when it issued a permit to a developer that planned to fill wetlands for a mixed…
The court holds that the U.S. Army Corps of Engineers did not violate the National Environmental Policy Act (NEPA) or act arbitrarily or capriciously in granting a developer a permit to fill…
The court holds that the U.S. Army Corps of Engineers properly granted a riverboat casino operator a Clean Water Act (CWA) and Rivers and Harbors Appropriations Act permit to construct and operate…
The court holds that an environmental group is not entitled to a preliminary injunction suspending a proposed retail development's construction permit and ordering the U.S. Army Corps of…