Mahelona v. Hawaiian Elec. Co.
ELR Citation: ELR 20031 No(s). 76-0130 (D. Haw. Aug 27, 1976)
The Army Corps of Engineers failed to comply with the requirements of NEPA in connection with its issuance of a permit for construction of a power plant's cooling water discharge facility in navigable waters. The planned design includes erection of a concrete wall across a prime surfing site. The Co...