Geraghty & Miller, Inc. v. Conoco, Inc.
ELR Citation: ELR 20369 No(s). 99-20020 (5th Cir. Dec 14, 2000)
The court holds that property owner's Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) response cost claims against an environmental contractor are not time barred and that the contractor may be liable as an operator or arranger, but not as a transporter. The contractor...