28 ELR 21533 | Environmental Law Reporter | copyright © 1998 | All rights reserved


United States v. Navistar International Transportation Corp.

No. 97-3829 (152 F.3d 702, 47 ERC 1207) (7th Cir. August 12, 1998)

The court holds that Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) § 113 bars the federal and Indiana governments' actions to recover cleanup costs incurred at the Maumee River site in Fort Wayne, Indiana. The governments initially sued the owner and operator of the site. Subsequently, a consent decree was entered into providing for payment of the governments' response costs. In order to recover response costs not covered by the consent decree, the governments later filed suit against third-party defendants to the original suit.

The court first holds that the appropriate limitations period under CERCLA is the six-year period for initial actions. The court agrees with the governments that nothing in CERCLA, its history, or the case law makes the entry of a declaratory judgment a prerequisite for a subsequent action. However, a subsequent action against a party can be brought only after an initial action has been brought against that party. Here, the governments' actions against the third-party defendants were the first claims they brought against these defendants to recover response costs. The court next holds that the governments' actions filed on September 19 and 20, 1996, were filed more than six years after the initiation of physical on-site construction of the remedial action, and, therefore, they are time barred under CERCLA § 113(g)(2)(B). The court refuses to adopt a bright-line rule that the initiation of construction can never begin until the U.S. Environmental Protection Agency (EPA) issues final, written approval of the remedial design for the site at issue. If Congress had intended to require EPA to issue its final approval of the remedial design in order for a remedial action to begin within the meaning of CERCLA § 113(g)(2)(B) — a contention unsupported by the definition of "remedial action" — Congress surely would have provided a more explicit direction to that effect. In crafting the state of limitations, Congress specifically made the initiation of physical on-site construction of the remedial action the triggering event. Moreover, it cannot be disputed that the placement of a clay cap on September 18, 1990, was a physical action. It is further undisputed that the remedial action for the site called for the construction of a permanent clay cap. Although it is true that the initial clay placed on the site was deemed inadequate to satisfy certain specifications required for the clay cap, the court does not consider that fact relevant because CERCLA does not indicate that the initial construction must be successful.

The court also holds that the six-year statute of limitations under CERCLA applies to Indiana's action under state law for recovery of response costs. The plain language of the Indiana statute indicates that the provisions defining liability under CERCLA provides the basis for the scope of liability under the Indiana cause-of-action. In addition, the court thinks it likely that CERCLA's statute of limitations would be the one the Indiana Supreme Court would adopt if it was faced with this question. Consequently, the court holds that the state action is time barred as well.

A dissenting judge would hold that the six-year statute-of-limitations period was not triggered until EPA provided written approval of the final design for remedial action.

Counsel for Plaintiffs
David C. Christensen
Environment and Natural Resources Division
U.S. Department of Justice, Washington DC 20530
(202) 514-2000

Counsel for Defendants
Mary R. Alexander
Latham & Watkins
Sears Tower
233 S. Wacker Dr., Ste. 5800, Chicago IL 60606
(312) 876-7672/7700

Before Kanne and Evans, JJ.

[28 ELR 21533]

Ripple, J.:

This is an interlocutory appeal. The United States and the State of Indiana (the "governments") filed separate actions under the Comprehensive Environmental Response, Compensation, and Liability Act ("CERCLA"), 42 U.S.C. §§ 9601-9675, to recover costs incurred by them in connection with environmental clean-up and remediation of a site in Fort Wayne, Indiana. In addition to its federal CERCLA claim, Indiana also brought a state law action seeking similar relief. See Ind. Code § 13-25-4-8. These actions against Navistar International Transportation Corporation and the twenty-five other defendants (hereinafter referred to collectively as "Navistar") were consolidated by the district [28 ELR 21534] court. Navistar sought summary judgment on the ground that the governments' claims were time barred by the six-year CERCLA statute of limitations, 42 U.S.C. § 9613(g)(2)(B). The district court denied the motion for summary judgment, and Navistar sought and received certification to appeal the ruling immediately under 28 U.S.C. § 1292(b). This court accepted the certification and permitted the interlocutory appeal. For the reasons set forth in the following opinion, we reverse the district court's judgment denying Navistar's motion for summary judgment.

I

Background

A. Facts

The environmental site at issue in this litigation is located on the Maumee River in Fort Wayne, Indiana. The site was used as a municipal landfill from approximately 1967 to 1976 for the disposal of residential and industrial wastes, including hazardous wastes. The United States Environmental Protection Agency ("EPA") placed the site on the National Priorities List in 1986, indicating that it was considered a significant threat to the public health and the environment. See generally 42 U.S.C. § 9605(a)(8); 40 C.F.R. § 300.425. This action resulted in the initiation by the EPA of a formal administrative process regarding the site, including an evaluative process to determine what action was necessary to neutralize the threat posed by the site. See generally 40 C.F.R. §§ 300.400-440 (outlining methods and procedures for evaluating, prioritizing and remedying environmental harms). At the conclusion of this process, the EPA determined that, among other things, the landfill needed to be covered with a permanent clay cap to isolate the hazardous materials from the rest of the environment.

In February 1989, the governments filed an action against SCA Services of Indiana, Inc. ("SCA"), the owner and operator of the site at that time. Simultaneously, the parties filed a consent decree which provided that SCA would perform and pay for the necessary remedial action at the site under the governments' supervision and in accordance with the various documents produced during the formal EPA administrative process. SCA also agreed to pay a portion of the governments' costs to oversee the remedial action up to a maximum of $ 200,000. The consent decree was approved by the district court in July 1989.

The consent decree, in combination with several administrative documents, established a timeline for the preparation and creation of the remedial design plan for the site and for the implementation of that plan. Moreover, the decree indicates that the implementation of the remedial action was to begin after the final remedial design plans were approved by the EPA and the State. The EPA asserts that this approval had to be in writing.1 In July 1990, SCA obtained permission to begin certain activities in connection with the remedial action. These activities included hooking up utilities at the site for use in the remedial action, constructing an access road and clearing and grubbing part of the site to prepare for placement of the clay cap. The governments note that the final design of the remedial action had not been submitted at this time, and so approval to begin the implementation phase of the action had not been obtained.

On September 11, 1990, the final design documents were submitted to the EPA. On September 14, 1990, the EPA's project manager gave SCA oral approval of the final design, and on September 17, 1990, oral authorization was given to SCA to proceed with construction of the remedial action. On September 18, 1990, the first "lift" of clay to build the permanent clay cap was placed on the landfill.2 On September 20, 1990, SCA obtained written approval of the design plan and written authorization to begin construction. The construction of the remedy was completed by SCA in 1995, but the governments continued to incur oversight costs because some response activities at the site, such as groundwater monitoring, are ongoing.

Navistar and the other defendants in this action became involved in the EPA-SCA litigation in 19923 when SCA filed a third-party complaint naming them, as well as more than fifty other parties, as thirdparty defendants and seeking contribution for the costs of the remedial action. However, the governments did not file any claims directly against the defendants at that time; in fact, the United States attempted unsuccessfully to sever the third-party litigation from the settled action between itself and SCA. The litigation between SCA and the third-party defendants ultimately was settled through various agreements to which the governments were not a party. Because some of the agreements could have been construed to preclude any cost-recovery claims by the United States against the parties to the settlements, the governments obtained an order from the district court reserving their rights to bring separate claims against the third-party defendants to recover their oversight costs. This action was filed by the United States against Navistar on September 19, 1996, to recover its costs for the remedial action that were not covered by the SCA consent decree. The State of Indiana filed a similar action on September 20, 1996.

B. Proceedings in the District Court

The complaints filed by the governments sought reimbursements for costs incurred from November 1, 1989, through April 30, 1995, and a declaration that the defendants are jointly and severally liable for future costs. The defendants moved for summary judgment onthe ground that the action was brought beyond the six-year statute of limitations and thus was time barred. The statute of limitations at issue provides:

(2) Actions for recovery of costs

An initial action for recovery of the costs referred to in section 9607 of this title must be commenced —

. . .

(B) for a remedial action, within 6 years after initiation of physical on-site construction of the remedial action . . . .

In any such action described in this subsection, the court shall enter a declaratory judgment on liability for response costs or damages that will be binding on any subsequent action or actions to recover further response costs or damages. A subsequent action or actions under section 9607 of this title for further response costs at the vessel or facility may be maintained at any time during the response action, but must be commenced no later than 3 years after the date of completion of all response action. . . .

42 U.S.C. § 9613(g)(2). The pertinent language of the statute is that "[a]n initial action for recovery of the costs . . . must be commenced . . . for a remedial action, within 6 years after initiation of physical on-site construction of the remedial action." Id. Navistar's position was that initiation of the on-site construction began no later than September 18, 1990, when the first lift of clay was placed on the landfill. Therefore, because the governments' actions were filed on September 19 and 20, 1996, they were filed after the six-year period had expired.

The district court concluded that the six-year statute of limitations was inapplicable in this case because the suit against the defendants was not an "initial action," but was instead a "subsequent action" governed by a different limitations period. The CERCLA statute provides that a "subsequent action . . . for further response costs . . . may be maintained at any time during the response action, but must be commenced no later than three years after the date of completion of all response action." Id. The district court determined that the case by the governments against SCA was the initial action and that this case against Navistar was a subsequent action to obtain further response costs. In the district court's view, because this action was commenced while the "response action" was ongoing, it is not time barred. Alternatively, the district court held that, even if this case is an initial action governed by the six-year statute of limitations, the action was timely [28 ELR 21535] filed because the activities cited by Navistar did not constitute the "initiation of physical on-site construction of the remedial action" within the meaning of the statute.4

Because the district court decided that the governments' federal claims were not time barred, it held that the secondary issue of the appropriate statute of limitations to apply to Indiana's state law-based claim was moot; Indiana had argued that a state law ten-year limitations period applied, and Navistar had argued that the federal six-year period applied. Because the court found that the actions were timely with respect to the six-year period, that dispute was rendered moot. As set forth below, we determine that the governments' federal claims are time barred, and consequently we also address whether Indiana's state law action is similarly time barred and hold that it is.

II

Discussion

This case presents us with two questions involving the construction of the CERCLA statutes of limitations contained in 42 U.S.C. § 9613(g)(2). The first is whether the six-year statute of limitations for "initial actions" or the open-ended statute of limitations for "subsequent action[s] . . . for further response costs" applies to the actions filed by the governments against Navistar in September 1996. If we were to determine that the longer period for subsequent actions applies, this appeal would be at an end; however, because we conclude that the six-year period is the correct one, we must also decide whether the governments' actions were filed more than six years following the "initiation of physical on-site construction of the remedial action." We decide that they were. Finally, we shall address the appropriate statute of limitations for Indiana's state law-based claim.

A.

We review the district court's decision to deny Navistar's motion for summary judgment de novo, viewing the facts of record in the light most favorable to the governments. See Harden v. Raffensperger, Hughes & Co., 65 F.3d 1392, 1396 (7th Cir. 1995). A party is entitled to summary judgment when the "pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law." Fed. R. Civ. P. 56(c). In this case, the facts are not in dispute; rather, the parties disagree with respect to the interpretation of the CERCLA statute of limitations and with respect to the application of that law to the facts. The district court's interpretation of the CERCLA statute is a matter of law that we shall review de novo. See United States v. Montoya, 827 F.2d 143, 146 (7th Cir. 1987).

The governments urge that, in conducting that review, we construe the statute of limitations in their favor in order to avoid frustrating the salutary goals of CERCLA.5 We acknowledge this general principle, but also note that Congress had a specific purpose in mind when it added the statute of limitations to CERCLA in 1986. By implementing the statute of limitations, it expressed a determination that, in order to achieve timely clean-up of affected sites and to ensure replenishment of the fund,6 cost recovery actions must commence in a timely fashion.7 Therefore, although we shall construe ambiguities in the statute in favor of the government in an effort to avoid frustrating the beneficial purposes of CERCLA, we must recognize that Congress has determined that those beneficial purposes are serviced by the timely filing of recovery actions. Cf. Galloway v. General Motors Serv. Parts Operations, 78 F.3d 1164, 1165 (7th Cir. 1996) ("[T]he Supreme Court has told us not to interpret statutes of limitations in a grudging, hostile fashion. . . . They serve the important purpose of encouraging the prompt filing of claims and by doing so of enhancing the likelihood of accurate determinations and removing debilitating uncertainty about legal liabilities." (internal citations omitted)).

B.

We turn first to the question of the appropriate CERCLA statute of limitations period to apply to the actions filed by the governments against Navistar. The parties appropriately focus their initial efforts on the wording of the statute. Section 9613(g)(2) provides the limitations periods for "initial action[s]" for the recovery of costs under 42 U.S.C. § 9607; moreover, the statute specifies different limitations periods for such cost recovery actions if they relate to "removal action[s]," see § 9613(g)(2)(A), as opposed to "remedial action[s]," see § 9613(g)(2)(B). There is no dispute here that a "remedial action" is involved. Therefore, the pertinent statutory language provides that an "initial action" to recover costs must be commenced "within 6 years after initiation of physical on-site construction of the remedial action." Navistar maintains that the governments' actions against it are such "initial action[s]" subject to the six-year period.

The governments contend, however, that their actions against Navistar are "subsequent action[s]." Section 9613(g)(2) states that a "subsequent action or actions under section 9607 . . . for further response costs at the vessel or facility may be maintained at any time during the response action, but must be commenced no later than 3 years after the date of completion of all response action." There is also no dispute that the "response action" at the site in this case is ongoing; consequently, if this period of limitations applies, the governments' actions were timely filed. In essence, in order to determine which period of limitations applies, we must determine whether the actions against Navistar are "subsequent" or "initial" ones.

The governments claim that the initial action for recovery of costs was the action they brought against SCA to establish primary liability for the site. That action was resolved by the consent decree, which provided for the recovery of various "response"8 costs including part of the governments' costs (up to $ 200,000) of overseeing the remediation process at the site. However, the consent decree did not cover all of the governments' costs; consequently, the governments brought these actions against Navistar to recover additional costs that they have incurred and to obtain a declaration that future costs also will be paid by Navistar. According to the governments, therefore, the actions against Navistar are "subsequent" ones to recover "further response costs at the . . . facility" within the plain meaning of the statute.

Navistar counters that the plain language and structure of the statute actually establish certain prerequisites for a "subsequent action." Because those prerequisites are not met here, it maintains, the governments' actions only can be deemed initial ones. Navistar contends that the sentence in § 9613(g)(2) prior to the one containing the limitations period for subsequent actions establishes one such prerequisite: "In [28 ELR 21536] any such action described in this subsection, the court shall enter a declaratory judgment on liability for response costs or damages that will be binding on any subsequent action or actions to recover further response costs or damages." In Navistar's view, this sentence obligates a district court to enter a declaratory judgment on liability in any and all initial actions that will then govern subsequent actions. Navistar notes that no such declaratory judgment has been entered with respect to this site in general, much less with respect to itself or any of the other defendants specifically; consequently, Navistar maintains that, under the plain language of the statute, the actions against it cannot be deemed "subsequent action[s]" if there has not been first a declaratory judgment entered on an initial action.

In support of this position, Navistar cites, beyond the plain wording and structure of the statute, various authorities. The legislative history, in its view, bolsters the idea that a subsequent action can only follow an initial action concluded by a declaratory judgment.9 In addition, Navistar cites certain proposed, but ultimately not adopted, rules promulgated by the EPA to highlight that the government itself has understood the statute to require a declaratory judgment.10 Finally, Navistar asserts that the Fourth Circuit understands the CERCLA statute to require entry of a declaratory judgment in an initial action before any subsequent action may be maintained.11

The governments respond that nothing in the statute, its history, or the case law requires that all initial actions be concluded by the district court's entering a declaratory judgment with respect to liability; i.e., the statute does not make the entry of a declaratory judgment a prerequisite for a subsequent action. The governments note that, although the statute does provide for entry of a declaratory judgment for efficiency purposes, none of the authorities relied on by Navistar establishes that such a judgment is a quid pro quo or a prerequisite for the maintenance of a subsequent action.12

We agree with the governments and the district court on this issue. The structure of this subsection indicates that the intent of Congress in including the sentence was to avoid the necessity of relitigating liability questions. It provides for the declaratory judgment as a way to manage the litigation in an efficient manner. That also is what we understand the legislative history relied upon by Navistar to indicate. See H.R. Rep. No. 99-253, pt. 3, at 21 (1985), reprinted in 1986 U.S.C.C.A.N. 3038, 3044 ("In the initial cost recovery action, in order to conserve judicial time and resources, the court is to enter a declaratory judgment on liability for response costs; . . ."). However, there is nothing to indicate that a declaratory judgment is the only permissible means to resolve an "action for recovery of the costs referred to in section 9607." 42 U.S.C. § 9613(g)(2). Nor is there anything to indicate that the entry of such a declaratory judgment is a prerequisite to the prosecution of a "subsequent action . . . for further response costs." Id.13

Although we are unpersuaded by Navistar's first argument to establish a prerequisite for subsequent actions, we do accept its second position. Navistar also argues that the governments' actions against it cannot be "subsequent actions" because the governments have never previously asserted any claim against it. Therefore, submits Navistar, a common sense understanding of "initial" versus "subsequent" actions indicates that the governments' actions against Navistar are initial ones.

The governments respond that it is not necessary for them to have brought claims against these particular defendants in order for this action to be considered a "subsequent" one. The governments reiterate that the initial action here was against SCA; moreover, they note that Navistar and the other defendants were parties to that litigation as third-party defendants. The governments also focus on the fact that the defendants were aware of the claims against them because, in the course of the SCA litigation, the defendants blocked, for discovery purposes, the governments' attempt to sever the action against SCA from the third-party actions. Therefore, the governments urge that, although they did not assert claims directly against Navistar, it was party to the initial action and was intimately aware of the governments' future claims against it.

We cannot accept the governments' position. We believe that, from the language and structure of the statute, a "subsequent action . . . for further response costs" must be one brought against the same party or parties against which an "initial action" to recover such costs has been maintained. The first time an action is brought against a given party, it cannot be anything other than an "initial action" for recovery costs. If this were not the case, as Navistar notes, the government would only need to bring an "initial action" against a single party within the six-year limitations period. Thereafter, any action brought by the government against any party in connection with that site could be deemed a "subsequent action" which, under the terms of the statute, may be brought "any time during the response action, but . . . no later than 3 years after the date of completion of all response action." 42 U.S.C. § 9613(g)(2). As Navistar points out, this rule would largely write the limitations restriction for initial actions out of the statute because many response actions will be ongoing for decades. In this case, for example, the remedial action at the site is anticipated to last another thirty years. Therefore, if the governments were permitted to file "subsequent actions" against new parties as long as an "initial action" was filed within the six-year period against one party (here, SCA), the governments would have had approximately 33 more years to bring its claims against Navistar. We do not think that this understanding of the statute comports with Congress' intent in adding the statute of limitations to CERCLA — "to provide some measure of finality to affected responsible parties." H.R. Rep. No. 99-253, pt. 1, at 138 (1985), reprinted in 1986 U.S.C.C.A.N. 2835, 2920. Therefore, we hold that a "subsequent action" against a party can be brought only after an "initial action" has been brought against it. Here, thegovernments' actions against Navistar were the first claims brought against these defendants by the governments to recover response costs. Therefore, the appropriate limitations period in this case is the six-year period for initial actions.14

[28 ELR 21537]

C.

Having established that the six-year limitations period for initial actions, see 42 U.S.C. § 9613(g)(2)(B), applies in this case, we turn next to the question of whether the actions were timely filed. As noted above, the statute provides that an "initial action for recovery of costs . . . must be commenced . . . for a remedial action, within 6 years after initiation of physical on-site construction of the remedial action." Id. Therefore, the focus for this inquiry is the latter portion of that language, i.e., whether the governments filed suit within six years after the "initiation of physical on-site construction of the remedial action." The only guidance given in the statute regarding this language is that "remedial action" is defined. See supra n.4. In part, that definition indicates that a remedial action constitutes "[t]hose actions taken consistent with [the] permanent remedy" including "such actions at the location of the release as storage, confinement, . . . [and] clay cover." 42 U.S.C. § 9601(24). We recall at the outset that the governments filed suit on September 19 (United States) and September 20 (Indiana) 1996. Therefore, if the initiation of construction of the remedial action began before September 19, 1990, the governments' actions are time barred.

In Navistar's view, SCA undertook a number of activities in August and September 1990 that constitute initiation of construction of the remedial action.15 Specifically, SCA hooked up utilities at the site, set up trailers and connected them with the utilities, constructed an access road, cleared and grubbed a portion of the site to prepare it for the clay cap, compacted existing landfill at the site to prepare for the clay cap, and excavated, transported and stockpiled clay for construction of the clay cap. In addition to these activities, SCA placed the first lift of clay for the clay cap on the site on September 18, 1990. Navistar contends that these activities, particularly the placement of the clay, clearly constitute, in the terms of the statute of limitations, the "initiation of physical on-site construction of the remedial action."

In support of its position, Navistar explains that the primary aspect of the remedial action in this case was the construction of the clay cap on the site; in fact, such a "clay cover" is specifically mentioned in thedefinition of "remedial action." Therefore, when SCA placed the first lift of clay on the site on September 18, after it had received oral approval from the EPA to proceed, that action, according to Navistar, was the (1) physical (2) initiation (3) on the site (4) of the construction (5) of the remedial action. If this activity was not enough in itself to begin the statute of limitations running, Navistar refers us to the other activities it undertook to prepare the site for construction of the clay cap and directs our attention to various cases in which similar activities have been held to satisfy the conditions of "initiation of physical on-site construction of the remedial action."

In opposition, the governments present essentially two arguments to demonstrate why the activities undertaken by SCA prior to September 19, 1990, did not trigger the statute of limitations period. First, the governments argue that this court should establish a bright-line rule: The initiation of construction of the "remedial action" can never begin, within the meaning of 42 U.S.C. § 9613(g)(2)(B), until the EPA issues final, written approval of the remedial design for the site at issue. Because such approval was not forthcoming in this case until September 20, 1990, the governments argue that their actions were timely filed. The rationale supplied by the governments for this bright-line rule is that the term "the remedial action" in § 9613(g)(2)(B) is a term of art which refers to the specific action determined to be required as a result of the evaluative administrative process. Therefore, submit the governments, the term does not refer merely to the general "remedial action" as defined in 42 U.S.C. § 9601(24), but refers specifically to "the remedial action" determined for the site. In this way, the governments submit, Congress intended to incorporate the underlying administrative process into the statutory framework. Moreover, that process in general contemplates that construction of the remedial action will not begin until a plan for the proposed remedial action has been designed and approved. From this proposition, the governments make the deductive leap that Congress contemplated that "the remedial action" cannot begin until the EPA has issued its final written approval of the remedial design.16 The benefit of such a rule, in the governments' view, is that it will be easy to apply and will conserve judicial resources because it will limit the inquiry of the on-site actions that may have initiated construction of the remedial action to those that occur after final design approval has been issued.

Whatever might be the advantages of such an approach, we are not persuaded that Congress intended such a rule. The statute is devoid of any reference that would lead us to conclude from its plain language that Congress intended to incorporate this specific aspect of the administrative process in establishing the actions that would trigger the limitations period. On the contrary, "remedial action" is a term broadly defined by the statute — a fact of which Congress was no doubt well aware when it incorporated that term in the statute of limitations. If it had intended to require that the EPA issue its final approval of the remedial design in order for a "remedial action" to begin within the meaning of § 9613(g)(2)(B) — a contention unsupported by the definition of "remedial action" — Congress surely would have provided us with a more explicit direction to that effect. See California v. Hyampom Lumber Co., 903 F. Supp. 1389, 1393 [26 ELR 20647] (E.D. Cal. 1995) (rejecting similar argument that a "'remedial action' may not occur prior to the final administrative approval of the permanent remedy").17 Rather, in crafting the statute of limitations, Congress specifically made "the initiation of physical on-site construction of the remedial action" the triggering event.

The governments' fall-back position is that, even if pre-written-approval actions can trigger the running of the statute of limitations, only a narrow range of events could fall within such a definition and, here, no such event took place before September 20, 1990. The governments note that, although "remedial action" is broadly defined in the CERCLA statute, the statute of limitations provision includes a number of modifying terms which collectively define the scope of actions which can trigger the limitations period. The governments observe that the actions must be "physical," which, they submit, excludes those studies undertaken and the designs necessary for the remedial action. The actions must also be "on-site," thereby excluding work performed elsewhere, even if that work is related to the remedial action. In addition, the actions must constitute "construction," a term which the governments suggest means the creation of something new rather than a modification of something preexisting. The actions must also relate to "the remedial action," which is the permanent remedy that has been developed for the site. And, given the statutory definition of that term, the actions at issue must be "consistent with" that particular permanent remedy. Finally, the governments also suggest that the action or actions at issue must play a "critical role in [the] implementation of the permanent remedy." United States v. Akzo Nobel Coatings, Inc., 990 F. Supp. 897, 905 [28 ELR 21097] (E.D. Mich. 1998). Viewing the actions taken by SCA in light of this understanding of the statute, the governments assert, mandates the conclusion that "initiation of physical on-site construction of the remedial action" did not occur prior to September 20, 1990.

The governments argue that the activities undertaken by SCA, such as hooking up the utilities, grubbing, etc., were necessary for the evaluation and remedial design phases of the process. Therefore, those activities were not part of the "remedial action." In addition, the governments assert that the placement of clay on the site on September 18, 1990, also was not sufficient because that effort was ineffective18 and thus did not play a "critical role" in the construction of the permanent remedy. Therefore, in the governments' view, the statute of limitations did not begin running until sometime after September 20, 1990.

[28 ELR 21538]

We do not agree. It cannot be disputed that the placement of the clay was a physical action undertaken by SCA on the site. The dispute instead centers on whether that action constituted the initiation of construction of the remedial action. We cannot see how the action at issue could be anything other than the initiation of such construction. It is undisputed that the remedial action for the site called for the construction of a permanent clay cap. Navistar has demonstrated that SCA began building that cap on September 18, 1990. Although the cap was not completed until much later, the statute is not concerned with "completion" of the remedial action, only with its "initiation." Although it is true that the initial clay placed on the site was deemed inadequate to satisfy certain specifications required for the clay cap, we do not consider that fact relevant because the statute does not indicate that the initial construction must be successful. The action taken on September 18, 1990, was clearly the first step in constructing the permanent clay cap and therefore was the "initiation" of "construction," § 9613(g)(2)(B), and "consistent with [the] permanent remedy," § 9601(24). Therefore, the governments' actions filed on September 19 and 20, 1996, were filed more than six years after the "initiation of physical on-site construction of the remedial action" and they are time barred.19

D.

We turn lastly to the question of whether Indiana's separate state law cause of action for recovery of response costs under Indiana Code § 13-25-4-8 is controlled by a statute of limitations other than that contained in CERCLA. The State urges that the general residual ten-year limitations period applies to such actions. Navistar, in contrast, argues that the Indiana cause of action incorporates the CERCLA statute of limitations and that Indiana's state law action thus is time barred for the same reasons that the governments' federal claims are. Whether the Indiana statute incorporates the CERCLA statute of limitations is a question that requires us to interpret state law. We must endeavor to predict how the Indiana Supreme Court would answer this question if it were presented to it. See Konradi v. United States, 919 F.2d 1207, 1213 (7th Cir. 1990) ("The decision of a federal court . . . in any . . . case in which state law supplies the rule of decision, is an exercise in predicting how the highest court of the state would decide the case if it were presented to it.").

The Indiana statute provides that a "person that is liable under Section 107(a) of CERCLA (42 U.S.C. § 9607(a)) for . . . the costs of removal or remedial action incurred by the commissioner . . . is liable, in the same manner and to the same extent, to the state under this section." Ind. Code § 13-25-4-8. However, the Indiana statute does not contain any explicit provision regarding a statute of limitations for the state cause of action. Because the statute is silent on this point, argues the State, Indiana law indicates that the residual statute of limitations period applies. See Ind. Code § 34-1-2-3 ("All actions not limited by any other statute shall be brought within ten (10) years . . . .").20

Navistar counters that the residual statute of limitations is inapplicable because the Indiana statute creating the cause of action expressly incorporates the CERCLA statute of limitations. The Indiana statute creating the cause of action expressly establishes liability under that statute "in the same manner and to the same extent" as liability exists under CERCLA. Ind. Code § 13-25-4-8. Therefore, Navistar asserts, the CERCLA statute of limitations, a provision that limits the scope of liability under CERCLA, was expressly adopted in the Indiana statute. Navistar also contends that, as a practical matter, the Indiana statute, devoid as it is of any definitional or other significant substantive provisions, is workable only to the extent that it is read to incorporate all of the important aspects of federal CERCLA law. Therefore, the CERCLA statute of limitations is the only logical choice to apply to the Indiana cause of action because it defines the appropriate limitations periods for the different kinds of actions (remedial or removal) and provides guidance with regard to the actions that trigger the periods. See 42 U.S.C. § 9613(g)(2).

We believe that Navistar is correct. The plain language of the Indiana statute indicates that the provisions defining liability under CERCLA, in all of its aspects, provides the basis for the scope of liability under the Indiana cause of action. Indiana only modified slightly that scope of liability, see § 13-25-4-8(b)-(d), in the manner that it saw fit and otherwise appears to have contemplated the complete adoption of federal CERCLA law to govern the extent of liability under its statute. We think it likely, given the wholesale adoption of federal CERCLA law necessary to effectuate the Indiana statute as it is written, that if Indiana had decided to employ a statute of limitations other than that contained in CERCLA, it would have done so explicitly.

Moreover, even if the plain language of Indiana Code § 13-25-4-8 is read not to incorporate the CERCLA statute of limitations, we think it likely that statute would be the one the Supreme Court of Indiana would adopt if it was faced with this question. It would be consistent with Indiana law for that Court to look to the federal statute of limitations governing the adopted federal cause of action in defining what limitations period is appropriate. See Kirchoff v. Selby, 686 N.E.2d 121, 128 (Ind. Ct. App. 1997) ("[I]t is generally accepted in Indiana that when a state statute is modeled after a federal statute, we may look to the cases interpreting the federal statute for guidance in interpreting the Indiana statute."). Therefore, we conclude that the six-year statute of limitations under 42 U.S.C. § 9613(g)(2)(B) applies to Indiana's action under Indiana Code § 13-25-4-8 for recovery of response costs; consequently, for the same reasons we have explained that the federal causes of action were not timely filed, that action is time barred.

Conclusion

The governments' federal actions against Navistar in this case were initial ones governed by the six-year CERCLA statute of limitations. Because the initiation of physical on-site construction of the remedial action (here a clay cap) began more than six years before the actions were filed, they are time barred. In addition, Indiana's separate state law-based cause of action is also governed by the six-year CERCLA statute of limitations for initial actions; therefore, that claim is also time barred. Accordingly, the district court erred in denying Navistar's motion for summary judgment and that decision is reversed.

REVERSED.

1. The EPA extrapolates this requirement from a clause in the consent decree requiring that the EPA notify SCA in writing of its approval or disapproval of any document submitted by SCA within 45 days of its receipt. R.17, Ex. C at 15.

2. This clay later was determined not to meet the necessary density and moisture specifications and shortly thereafter construction of the cap was discontinued because it was clear that the cap could not be completed before winter set in; however, the record indicates that that clay is still on-site and forms some part of the permanent clay cap.

3. The governments note that, prior to their involvement in the SCA litigation, Navistar and all but one of the other defendants were aware of the governments' potential claims against them to the extent that they had agreed in 1990 to pay costs incurred by the governments in connection with the site prior to October 31, 1989. That settlement agreement was reached with 72 of the 132 parties which were identified as potentially responsible for contamination at the site and which were sent demand letters by the EPA for reimbursement of those costs.

4. The term "remedial action" is defined in pertinent part in the CERCLA statute as:

[T]hose actions consistent with permanent remedy taken instead of or in addition to removal actions in the event of a release or threatened release of a hazardous substance into the environment, to prevent or minimize the release of hazardous substances so that they do not migrate to cause substantial danger to present or future public health or welfare or the environment. The term includes, but is not limited to, such actions at the location of the release as storage, confinement, perimeter protection using dikes, trenches, or ditches, clay cover, neutralization, . . . and any monitoring reasonably required to assure that such actions protect the public health and welfare and the environment. . . .

42 U.S.C. § 9601(24) (emphasis supplied).

5. See Badaracco v. Commissioner, 464 U.S. 386, 391 (1984) ("'Statutes of limitation sought to be applied to bar rights of the Government, must receive a strict construction in favor of the Government,'" (quoting E.I. DuPont de Nemours & Co. v. Davis, 264 U.S. 456, 462 (1924))); Kelley v. E.I. DuPont de Nemours & Co., 17 F.3d 836, 843 [24 ELR 20538] (6th Cir. 1994) (noting Sixth Circuit's "willingness to give CERCLA provisions a broad construction, consistent with the legislative purposes of the act" (internal quotation omitted) and acknowledging First Circuit's broad construction of CERCLA's limitations periods); United States v. United Nuclear Corp., 814 F. Supp. 1552, 1561 [23 ELR 20887] (D.N.M. 1992) (stating that "[c]ourts have interpreted the [CERCLA] statute of limitations liberally in favor of EPA"); United States v. Petersen Sand & Gravel, Inc., 824 F. Supp. 751, 755 (N.D. Ill. 1991) (noting principle that statute of limitations should be construed in favor of the government and that "the remedial intent of CERCLA requires a liberal statutory construction in order to avoid frustrating its purpose").

6. Section 9601(11) defines "fund" to mean the "Hazardous Substance Superfund established by Section 9507 of Title 26." 42 U.S.C. § 9601(11).

7. See H.R. Rep. No. 99-253, pt. 1, at 138 (1985), reprinted in 1986 U.S.C.C.A.N. 2835, 2920 ("[T]he Federal government recognizes the need for filing of cost recovery actions in a timely fashion, to assure that evidence concerning liability and response costs i[s] fresh, to help replenish the Fund, and to provide some measure of finality to affected responsible parties."); H.R. Rep. No. 99-253, pt. 3, at 20 (1985), reprinted in 1986 U.S.C.C.A.N. 3038, 3043 (explaining the addition of the CERCLA statute of limitations and stating that "in general these [cost recovery] actions should be brought as early as EPA has the necessary information to do so"); see also New Castle County v. Halliburton NUS Corp., 903 F. Supp. 771, 780 [26 ELR 20628] (D. Del. 1995) ("[T]he imposition of a statute of limitations does not frustrate the purposes of CERCLA, which inter alia is to achieve prompt clean up of polluted sites . . . . The deadline imposed by the statute of limitations encourages settling parties to move quickly and begin the work of investigating and cleaning up the site . . . ."), aff'd in part, 111 F.3d 1116 [27 ELR 21159] (3d Cir. 1997).

8. The term "response" as used in the statute "means remove, removal, remedy, and remedial action;, [sic] all such terms (including the terms 'removal' and 'remedial action') include enforcement activities." 42 U.S.C. § 9601(25).

9. See H.R. Rep. No. 99-253, pt. 3, at 21 (1985), reprinted in 1986 U.S.C.C.A.N. 3038, 3044 ("In the initial cost recovery action, in order to conserve judicial time and resources, the court is to enter a declaratory judgment on liability for response costs; this judgment will be binding in future cost recovery actions to obtain additional costs.").

10. See 57 Fed. Reg. 34,742, 34,752 (1992) ("Under the provisions of section 113(g)(2)(B), where a declaratory judgment on liability has been entered by a court, the statutory limitation period for a subsequent action is extended to three years after 'completion of all response action.'").

11. See Beazer East, Inc. v. United States Navy, No. 96-1736, 1997 WL 173225 (4th Cir. Apr. 11, 1997) (unpublished disposition). In that case, Beazer, the former owner of the clean-up site, was sued by the present owner for clean-up costs. Beazer, in turn, brought third-party actions against the Navy and six other parties for contribution of costs. After Beazer paid for a remedial investigation study, it brought another, separate action against the Navy and twenty-seven other defendants for recovery of the costs for the study and for future remediation costs. When the original action by the present owner against Beazer was settled, Beazer moved to dismiss with prejudice the third-party actions that were part of that litigation. The district court granted the motion. Subsequently, the Navy moved for summary judgment in the separate action brought by Beazer on the ground of res judicata; that motion was granted. On appeal, Beazer argued that 42 U.S.C. § 9613(g)(2) entitled it to pursue the Navy in a "subsequent action," and therefore that its claim was not barred by res judicata. The court held that, in making this argument, Beazer ignored the "first sentence" of the statute (the one relied on by Navistar to establish the prerequisite) "which requires that the court enter a declaratory judgment as to liability 'that will be binding on any subsequent action.'" Beazer, 1997 WL 173225, at *2. Thus, concludedthe court, "even if a party wants to pursue its response costs seriatim, the court in the first action must enter judgment as to liability for the site. . . . It is only after this determination has been made that a party may file subsequent actions 'for further response costs' as they arise." Id. (internal citation omitted).

12. The governments distinguish Beazer on the ground that the court there was not faced with the question of whether a declaratory judgment was a prerequisite for a subsequent action, but with the narrower question of whether the statute permitted such a subsequent action in light of an earlier dismissal with prejudice of the same type of claim. Moreover, the governments point out that the court indicated that Beazer's "subsequent action" was an attempt to relitigate liability, and the court stated that avoiding such relitigation of liability was the purpose of the statutory language regarding "declaratory judgment[s]." Id. at *3. The district court agreed with the governments on this issue, finding that there is "simply no authority to suggest that a declaratory judgment, rather than, for example, a settlement order, is required to be entered in every case before the government may benefit from the . . . limitations period for subsequent actions." R.81 at 20. As we note in the text, we agree with the governments and the district court with regard to this issue.

13. The Sixth Circuit's decision in Kelley v. E.I. DuPont de Nemours & Co., 17 F.3d 836 [24 ELR 20538] (6th Cir. 1994), is not to the contrary. Although it contains the statement that "[t]he entry of declaratory judgment as to liability is mandatory." see id. at 844, the context makes it clear that the court is addressing the issue whether the indefinite nature of future clean-up costs is an adequate ground upon which to deny declaratory relief.

14. We are also not persuaded by the governments' arguments to the effect that Navistar was virtually a defendant in the initial action against SCA and therefore that these actions are "subsequent." Although Navistar was a third-party defendant in that action and may have been able to anticipate that the governments would seek to obtain costs from it, the governments did not assert any legal claim under 42 U.S.C. § 9607 against Navistar until they filed these actions.

15. We note that, although the parties dispute whether the activities that took place on the site before September 19, 1990, constitute the initiation of construction of the remedial action, they do not appear to dispute what activities actually took place.

16. The governments also rely on the specific administrative documents in this case and the SCA consent decree to establish that the remedial action could not begin until after final written approval of the design plans. Although there may be some support for their position in those documents, we shall not attempt to write into the statute a generally applicable bright-line rule based on the documents at issue in this particular case.

17. In addition, as Navistar points out, adopting the rule proposed by the governments would lead to the awkward result that actions brought by private parties to recover response costs would be subject to a different statute of limitations trigger when no government agency is involved in the clean-up. We do not think Congress intended such an inconsistency when it drafted the statute of limitations provision.

18. This assertion is based on the fact that the initial clay was determined not to comply with moisture and other standards required for the clay cap. In addition, the efforts to construct the clay cap were halted shortly thereafter because it became apparent that it could not be completed before the onset of winter.

19. Because we conclude that the placement of clay on the site triggered the statute of limitations period, we do not reach the question of whether any of the other actions SCA performed at the site in August and September 1990 were sufficient to do so.

20. The residual statute of limitations has since been repealed by Indiana. See P.L. 1-1998, § 221 (effective July 1, 1998).

Evans, J. (dissenting):

This is another case where Dinah Washington's1 sage advice — "What a diff'rence a day makes . . . twenty-four little hours" — should be recalled. See Spears v. City of Indianapolis, 74 F.3d 153 (7th Cir. 1996). Today, the court holds that this major CERCLA suit, filed on September 19 rather than September 18 of 1996, cannot proceed. Although the majority opinion presents a thorough analysis of the law governing this sticky issue, I disagree with the conclusion reached, and for that reason I dissent.

I would hold that this suit was filed within the 6-year statute of limitations provided for under CERCLA § 113(g)(2)(B). But Navistar insists that a little bit of work on the site prior to September 19, 1990, amounted to the "initiation of physical on-site construction of the remedial action." See CERCLA § 113(g)(2)(B). But "the remedial action" referred to in the statute cannot be initiated until the EPA provides written approval of the final design for that action. Here, written approval was given on September 20, 1990. Nothing that happened before that date, in my view, triggered the ticking of the statute of limitations clock.

This interpretation of the statute has an ease of application that would serve to advance the purposes of the statute of limitations, particularly in the complicated context of CERCLA suits. If actions cannot trigger the statute of limitations until formal written approval has issued, there will be no need for parties to haggle over the presence and nature of preapproval activity at a hazardous waste site. But that will be the result of today's opinion. Parties will now invest time, energy, and money in what is ultimately an issue peripheral to the real question — liability. The resulting distraction will undermine CERCLA's primary purposes: To provide a safe and efficient means of cleaning hazardous waste sites as quickly as possible, and to recover from those responsible the money spent to pay for that cleanup. See, e.g., Sidney S. Arst v. Pipefitters Welfare Educ. Fund, 25 F.3d 417, 420-21 [24 ELR 20976] (7th Cir. 1994).

[28 ELR 21539]

This interpretation of § 113(g)(2)(a) also has the advantage of providing the greatest possible protection to the public. Tying the statute of limitations to the date of written approval of the remedial design plan provides a concrete basis upon which federal, state, and private parties can rely in determining when the statute of limitations will bar a claim. It will also be easy for district courts to apply the rule. District judges will not have to engage in a complex weighing of factors to determine whether particular actions advanced the purpose of the remediation, and they will not have to guess what was in the minds of the actors on site when certain actions were taken. I would affirm the judgment of the district court.

1. Dinah Washington was not the first artist to record "What a Difference a Day Makes." Billboard magazine reports that it was first recorded by The Dorsey Brothers in 1934. Ms. Washington's summer of 1959 rendition, however, is regarded as a classic.


28 ELR 21533 | Environmental Law Reporter | copyright © 1998 | All rights reserved