18 ELR 20321 | Environmental Law Reporter | copyright © 1988 | All rights reserved
Oregon Natural Resources Council v. Marsh
No. 86-3670 (832 F.2d 1489) (9th Cir. June 23, 1987, amended November 24, 1987)The court holds that the Corps of Engineers' supplemental environmental impact statement (SEIS) for the Elk Creek Dam project in Oregon is deficient because its wildlife mitigation plan is incomplete, it fails to take into account new information acquired since the original EIS was prepared, and fails to include a worst case analysis in accordance with rescinded regulation 40 CFR § 1502.22, which remains binding because it was merely a codification of prior case law. The court first holds that the SEIS's mitigation plan for wildlife is inadequate because it contains neither a detailed analysis of mitigation measures nor an explanation of how effective those measures would be. Significant mitigation measures must be taken, even if they do not completely compensate for a project's adverse effects. The SEIS's mitigation plan for wildlife only listed general mitigation measures, and referred to "habitat manipulative techniques" without elaboration. Moreover, the listed measures were not analyzed in the SEIS nor was their effectiveness estimated. The court observes that the importance of the mitigation plan cannot be overestimated, and without it the decisionmaker cannot make an informed judgment as to the environmental impact of the project.
The court next holds that the Corps should have prepared a new SEIS taking into account new information acquired since it prepared the original EIS in 1980. A federal agency has a continuing duty to gather and evaluate new information relevant to the environmental impact of its actions after release of an EIS. When new information comes to light, the agency must determine whether it presents significant new circumstances or information relevant to environmental concerns and bearing on the proposed action or its impacts. The court holds that new information obtained since 1980 is significant and probably accurate, but that the Corps failed to exercise the proper degree of care in evaluating it and failed to properly support its decision not to the supplement the EIS. The court rules in a note that although the Council on Environmental Quality has rescinded the regulation requiring worst case analyses, 40 C.F.R. § 1502.22, the rules embodied in the regulation are merely a codification of prior case law and so remain in effect. The court holds that although the SEIS disclosed the scientific uncertainty on the project's effects on turbidity, this is not enough; a worst case analysis is also required when there are gaps in the information engendering scientific uncertainty that the agency determines to be important and when the necessary information cannot be obtained because of scientific impossibility or because the costs of obtaining it would be exorbitant. The Corps must either prepare a worst case analysis or conduct further research on the project's effects on turbidity.
The court holds that the Corps properly omitted other previously completed dams in its EIS, since only proposed projects need be considered. However, effects of the project under consideration must be considered as they cumulate with effects from prior projects, and the court holds that the Corps did not take a hard look at the cumulative environmental impacts.
The court holds that the Corps' responses to critical comments on its draft SEIS need not necessarily be integrated into the body of the final SEIS, and may be included in a separate "comments and responses" section when, as here, the body of the final SEIS was revised in light of the comments and all issues raised in the comments were covered in the body. Moreover, the court holds that the Corps need not address impacts on the portion of the river 57 miles downstream that is designated as wild and scenic, since the Corps reasonably concluded that those impacts would be insignificant. Finally, the Corps' use of a 3 1/4 percent discount rate in the body of the SEIS, as required by the Water Resources Development Act of 1974, and a 7 1/2 percent discount rate in an appendix was not misleading, although the purpose of an environmental document might have been better served if the text had made reference to the analysis in the appendix.
[This opinion replaces the court's original opinion, at 17 ELR 21024. The opinion below appears at 16 ELR 20475. An injunction pending appeal was denied in a decision at 16 ELR 20826.]
Counsel for Plaintiffs-Appellants
Neil S. Kagan
Suite 224, 1012 SW Oak, P.O. Box 2447, Roseburg OR 97470
(503) 673-6682
Counsel for Defendants-Appellees
Dorothy R. Burakreis
Land and Natural Resources Division
Department of Justice, Washington DC 20530
(202) 633-5390
Before Wallace and Norris, JJ.
[18 ELR 20321]
Ferguson:
Plaintiffs, the Oregon Natural Resources Council, Oregon Guides and Packers Association, Rogue Flyfishers, Inc., and Rogue River Guides Association ("Resources Council"), appeal the denial of an injunction to stop construction by the United States Army Corps of Engineers ("Corps") of a dam on Elk Creek in Southern Oregon. The Resources Council contends that the Corps' final supplemental environmental impact statement ("EIS") for the dam project fails to comply [18 ELR 20322] with the National Environmental Policy Act of 1969, Pub. L. No. 91-190, 83 Stat. 853 (1970) (codified at 42 U.S.C. § 4332) ("NEPA"). We affirm in part and reverse in part.
I.
Elk Creek is a tributary of Oregon's Rogue River. The Rogue was one of eight rivers in the nation designated as "wild and scenic" in the Wild and Scenic Rivers Act of 1968, Pub. L. No. 90-542, 82 Stat. 906 (1968) (codified at 16 U.S.C. § 1271). The Rogue is known nationally for its white-water rafting and fly-fishing.
In 1962, Congress authorized construction of three dams to control flooding of the Rogue River Basin: Elk Creek Dam, Applegate River Dam, and Lost Creek Dam. The latter two dams are completed. The Elk Creek project consists of a proposed concrete dam 249 feet high and 2,580 feet long. The reservoir behind the proposed dam would collect runoff from most of Elk Creek's watershed and cover 1,290 acres of land.
In 1971, the Corps filed a final EIS for the Elk Creek Project. In 1975, after studying the projected effects of the dam on turbidity[1] in the Rogue River, the Corps filed a draft supplemental EIS. Construction of the project was suspended until completion of further water quality studies.
In 1980, the Corps filed a revised draft supplemental EIS, which included turbidity and temperature projections based on the Corps' observations of turbidity caused by the Lost Creek Dam during the year 1977 and the Corps' computer simulation models. Several state and federal agencies criticized the Corps' turbidity analysis on the ground that rain runoff levels during 1977 were the lowest on record in the area. The Corps placed these critical comments, and its responses to them, in a separate section, and released the aggregate as its final supplemental EIS.
The Resources Council[2] then brought this action in federal district court for a temporary restraining order, a preliminary injunction, and a permanent injunction to stop construction of Elk Creek Dam. The Resources Council argued that the final supplemental EIS failed in several ways to comport with the requirements of the NEPA and regulatory guidelines of the Council on Environmental Quality. The Resources Council also contended that the Corps was required to prepare a new supplemental EIS because of new information. The district court found the final supplemental EIS adequate and denied the requested relief. The Corps has since awarded contracts for relocation of roads and utilities and for construction of the dam.
II.
The Resources Council contends that the final supplemental EIS violates the NEPA procedural standards and the Council on Environmental Quality guidelines in six respects. The district court held that the environmental impact statement comported with these standards. We review de novo the district court's determination of whether the EIS is reasonably thorough in discussing the significant aspects of the probable environmental impact of the proposed agency action. Enos v. Marsh, 769 F.2d 1363, 1372 (9th Cir. 1985) (applying a "rule of reason"). Purely factual findings are, of course, reviewed for clear error. Id.
We thus endeavor to determine whether the final supplemental EIS satisfies the two purposes of an EIS: (1) to provide decisionmakers with enough information to aid in the substantive decision whether to proceed with the project in light of its environmental consequence; and (2) to provide the public with information and an opportunity to participate in gathering information. Citizens for a Better Henderson v. Hodel, 768 F.2d 1051, 1056 (9th Cir. 1985); California v. Block, 690 F.2d 753, 761 (9th Cir. 1982)(the "form, content and preparation [of the EIS] foster both informed decisionmaking and informed public participation"); 40 C.F.R. § 1502.1 (purpose of EIS is to "provide full and fair discussion of significant environmental impacts and . . . [to] inform the decisionmakers and the public of the reasonable alternatives which would avoid or minimize adverse impacts . . .").
First, the Resources Council contends that the final supplemental EIS is deficient because it fails to discuss adequately ways to mitigate adverse environmental impacts of the project. Specifically, the Resources Council claims that the mitigation plan for wildlife contains neither a detailed analysis of mitigation measures nor an explanation of how effective those measures would be. We agree, and reverse for further proceedings on this issue.
An EIS must include a discussion of measures to mitigate adverse environmental impacts of the proposed action. 40 C.F.R. § 1502.16(h). As long as significant measures are undertaken to mitigate the project's effects, the measures need not compensate completely for adverse environmental impacts. Friends of Endangered Species, Inc. v. Jantzen, 760 F.2d 976, 987 (9th Cir. 1985). The mere listing of mitigation measures, however, is insufficient to satisfy the NEPA requirements. Northwest Indian Cemetery Protective Ass'n v. Peterson, 795 F.2d 688, 697 (9th Cir. 1986). Moreover, the EIS must analyze the mitigation measures in detail and explain the effectiveness of the measures. See id.
Here, the mitigation plan for wildlife is not yet fully developed. The mitigation plan, published in 1980, states: "Measures to compensate project-caused loss of wildlife habitat associated with reservoir construction will be developed, based upon the results of the wildlife compensation plan currently underway at Applegate Project and recommendations of Oregon Department of Fish and Wildlife and the U.S. Fish and Wildlife Service." No mitigation plan had been finalized as of January 1986. We fail to see how mitigation measures can be properly analyzed and their effectiveness explained when they have yet to be developed.
Moreover, the mitigation measures set forth in the final supplemental EIS are inadequate to satisfy the Council on Environmental Quality guidelines. The mitigation plan for wildlife, in its entirety, states:
The compensation [for project-caused loss of wildlife habitat] would be accomplished by managing selected lands to increase the quality of habitat and therefore its carrying capacity for wildlife. The management would consist of a number of habitat manipulative techniques in conjunction with other [18 ELR 20323] land uses, landscaping at the project, and development of recreation sites. Specific habitat development measures would be oriented toward development of palatable browse plants, creation of "edge," maximizing foliage height diversity in certain areas, and creation of snags in the reservoir. This compensation plan will be developed in coordination with Federal and state resource agencies.
This plan lists general measures to mitigate the impact of the project on wildlife. The plan refers to "habitat manipulative techniques," but fails to specify which techniques will be used. It also fails to identify any of the "specific habitat development measures" that would be utilized to develop palatable browse plants, create "edge," maximize foliage height diversity, or create snags in the reservoir. More important, there is no analysis of the mitigation measures listed, or any estimation of how effective the measures will be.
The importance of the mitigation plan cannot be overestimated. It is a determinative factor in evaluating the adequacy of an environmental impact statement. Without a complete mitigation plan, the decisionmaker is unable to make an informed judgment as to the environmental impact of the project -- one of the main purposes of an environmental impact statement. See Citizens for a Better Henderson, 768 F.2d at 1056.
Because the wildlife mitigation plan here merely lists measures to be used and includes neither an analysis nor an explanation of effectiveness, it is inadequate to satisfy the NEPA or Counsel on Environmental Quality mitigation guidelines. See Northwest Indian Cemetery Protective Ass'n, 795 F.2d at 697.
III.
The Resources Council also contends that the Corps violated the NEPA by failing to prepare a new supplemental EIS taking into account new information acquired since the 1980 EIS. We agree, and remand for further proceedings on this issue as well.
A federal agency has a continuing duty to gather and evaluate new information relevant to the environmental impact of its actions after release of an EIS. Stop H-3 Ass'n v. Dole, 740 F.2d 1442, 1463 (9th Cir. 1984), cert. denied, 471 U.S. 1108 (1985). The agency must supplement the EIS if "[t]here are significant new circumstances or information relevant to environmental concerns and bearing on the proposed action or its impacts." 40 C.F.R. § 1502.9(c)(1)(ii); see Enos, 769 F.2d at 1373. When new information comes to light, the agency must consider it, evaluate it, and make a reasoned determination whether it is of such significance as to require implementation of formal NEPA filing requirements. Stop H-3 Ass'n, 740 F.2d at 1463-64.
We will uphold an agency's decision not to supplement an environmental impact statement in light of new information if the decision is reasonable. Enos, 769 F.2d at 1373.
Reasonableness depends on the environmental significance of the new information, the probable accuracy of the information, the degree of care with which the agency considered the information and evaluated its impact, and the degree to which the agency supported its decision not to supplement with a statement of explanation or additional data.
Stop H-3 Ass'n, 740 F.2d at 1464 (citation omitted). Applying the Stop H-3 Ass'n standard,[3] we conclude that subsequent to the preparation of the final supplemental EIS, significant new information came to light. We further conclude, based upon the proceedings in the district court, that this information is probably accurate. The Corps failed to exercise the proper degree of care in evaluating the impact of the new information and failed to properly support its decision not to supplement the EIS with an explanation or additional data. Thus, a new supplemental EIS should have been prepared.
Two studies provided significant new information regarding the environmental impact of the project. The Oregon Department of Fish and Wildlife concluded that the project could result in decreased survivability of chinook salmon, higher turbidity, increased disease potential infish, and decreased prospects for lure- and fly-fishing.[4] The United States Soil Conservation Service found a greater turbidity potential than indicated by the final supplemental EIS. These studies contained the significant new information contemplated by Stop H-3 Ass'n.
The final draft of the Fish and Wildlife Department study, dated August 5, 1985, was based on the impact of Lost Creek Dam on salmon and steelhead populations downstream. Department scientists observed decreased survival of chinook salmon, and speculated that it was a result of increased water temperatures caused by the release of warmer water from the Lost Creek Reservoir. Based on Lost Creek Dam's impact on survivability, the Department believed that conditions from Elk Creek Dam also would affect negatively chinook salmon survivability. Department scientists concluded that, even though their study was not conclusive, this phenomenon should be studied further before Elk Creek Dam is built.
With regard to higher turbidity, information was based on a study of logging and road-building activity in the Elk Creek watershed since 1980. The logging and road-building has caused soil disturbance. Fish and Wildlife Department scientists believe that this activity will result in higher turbidity than that reported in the final supplemental EIS. Consequently, they suggest additional studies on turbidity potential before the dam is built.
As to disease potential in fish, Fish and Wildlife Department statistics indicate that in 1979, following the construction of Lost Creek Dam, there was a 76% mortality rate in fall chinook salmon populations due to disease and a 32% mortality rate in 1980. Although there has been almost no mortality since 1981, Department scientists concluded there may be a connection between dam closure and the potential for increased disease among fish.
Finally, the Fish and Wildlife Department was concerned about higher flows in the Rogue River that could decrease the effectiveness of lure- and fly-fishing along the river, including the wild and scenic portion. The Department wanted to conduct studies to evaluate this concern, but the Corps reduced the Department's budget, making further study impossible. [18 ELR 20324] The Corps evaluated the Department study and concluded that the new information was not significant enough to warrant a new supplemental EIS.
The Soil Conservation Service soil study also revealed significant new turbidity information tending to corroborate the Department study. The Soil Conservation Service study indicates that the Elk Creek watershed has substantially greater turbidity potential than previously reported in the EIS. Uncontradicted testimony showed that the soil content in the watershed is different than indicated in the final supplemental EIS. The Corps conducted no studies after receiving this new information because it had investigated erosion potential in 1979 and found nothing to substantiate the Department's concerns over the soil study. Thus, the Corps concluded that no significant new information had been discovered.
The district court found that the Corps' decision not to release a new supplemental EIS was reasonable. Like thedistrict court, we review the agency's decision for reasonableness. See Enos, 769 F.2d at 1373. We conclude otherwise. The Department presented new information as a result of its study of Lost Creek Dam's impact on the river. Although the evidence is not conclusive, it presented a legitimate concern about decreased survivability of fish and the potential for higher turbidity based on information from the two studies that was not available at the time the final supplemental EIS was published. The evidence clearly is environmentally significant under the Stop H-3 Ass'n test.
The information must be more than environmentally significant. It must be "probably accurate" as well. Stop H-3 Ass'n, 740 F.2d at 1464. Based on our review of the experts' testimony and data, we believe that, at the very least, some of the proffered information is probably accurate. Although the Corps had two independent experts evaluate the Fish and Wildlife Department's study, and these experts were critical of many of the conclusions reached, the experts also agreed with significant portions of the study. The Corps did not dispute that there was increased logging and road-building activity in the Elk Creek watershed since 1980. The Fish and Wildlife Department is concerned that this activity will result in increased turbidity.
The Corps also did not respond to the study's conclusions concerning increased fish mortality from epizootic diseases.[5] The information admittedly was not conclusive. Yet, the study raised legitimate concerns regarding the relationship between dam construction and epizootic diseases. The Corps should have considered the information, evaluated its impact and, at the very minimum, supported its decision not to supplement with a statement of explanation or additional data. Id. The Corps does not appear to have exercised the proper degree of care regarding the new information. The Corps also has not supported its decision with a statement of explanation or additional data.
The testimony below also reveals that the information provided by the Soil Conservation Service was never considered by the Corps, even when the Corps issued its Supplemental Information Report in September 1985. In response to questions submitted by the Council of Environmental Quality (CEQ) in 1981, the Corps stated that soils in the Elk Creek Watershed erode more easily than those in the Lost Creek Watershed and therefore produce a higher volume of suspended material per unit of stream runoff and require a longer time to settle out. The Corps concluded that this factor was considered in the modeling effort. Later, in response to commentary (identified as "Letter 14," attached to the final supplemental EIS) submitted in response to the draft EIS, the Corps stated that morphological factors cannot be incorporated into the WESTEX model[6] but are qualitatively included in the overall analysis of the potential turbidity of the watershed.
However, when presented with evidence showing that the soil content in the Elk Creek watershed was different from that indicated in the final supplemental EIS, the Corps chose not to respond. Table Four of the final supplemental EIS indicates that erosion potentials differ with soil associations. Further, the EIS states that turbidity is "generally caused by soil particles in the water column which are washed downstream in the runoff from the watershed." Soil type and turbidity may not be directly related, as the Corps contends. Yet, the data reveals that soil type is related to erosion potential which, in turn, affects turbidity. The Corps took this into account earlier in its analysis and should do so again using the new information. Even if this data cannot be included in the WESTEX model, the Corps should include it qualitatively in its "overall analysis" of turbidity.
These are significant matters, the accuracy of which is not disputed. The Corps did not address adequately these issues. Thus, applying the final two factors of Stop H-3 Ass'n, we conclude that the Corps must prepare a supplemental EIS to address these issues.[7]
IV.
The Resources Council also contends that the Corps was required by the CEQ "worst case" regulation to research further the effects of Elk Creek Dam on turbidity in the Rogue River during high, average, and normal-low rainwater runoff years.
The worst case analysis regulation, 40 C.F.R. § 1502.22, requires that when there are gaps in relevant information or scientific uncertainty with regard to significant adverse environmental effects, the agency must make it clear that the information is lacking or that uncertainty exists. If information is lacking that is essential to a reasoned choice and the cost of obtaining it is not exorbitant, the agency must obtain the information and include it in the statement or include a worst case analysis.[8]
The Oregon Department of Fish and Wildlife formally criticized the Corps' conclusion that Elk Creek Dam would have little effect on temperature and turbidity on the Rogue. The state agency specifically disagreed with the Corps' finding that Elk Creek would make only a small contribution to total flow in the Rogue River and commented that there may be periods [18 ELR 20325] when Elk Creek provides a significant percentage of the total flow of the Rogue. The Corps, in responding to the state agency's comment (identified as "Letter 6," attached to the final supplemental EIS), acknowledged that Elk Creek could contribute up to 25% of the flow in the Rogue during high flow periods. Thus, the Corps' assessment of turbidity due to Elk Creek Dam is subject to uncertainty. This uncertainty is disclosed in the final supplemental EIS.
The district court concluded that the Corps complied with the worst case analysis requirement because the final supplemental EIS included comments that exposed uncertainty, if uncertainty did in fact exist. Yet, exposing uncertainty is not enough. Save Our Ecosystems v. Clark, 747 F.2d 1240, 1244 n.5 (9th Cir. 1984), requires that the Corps include a worst case analysis in the EIS when there are gaps in the information engendering scientific uncertainty which the agency determines to be important and when the necessary information cannot be obtained because of scientific impossibility or because the costs of obtaining it would be exorbitant. See also Oregon Environmental Council v. Kunzman, Nos. 85-4266, 85-4308, and 86-3779, Slip Op. at 18 (9th Cir. May 12, 1987). The Corps did not include a worst case analysis and did not conduct any further research with regard to the water flow contribution from Elk Creek. The Corps should pursue one of these alternatives.
Additionally, since the Corps is now required to consider new information brought forth by the two studies, the Corps should take this information into account in its decision concerning a worst case analysis. If uncertainty remains at that time, the Corps should prepare a worst case analysis or conduct further research with regard to the new information.
V.
The Resources Council further contends that the Corps unreasonably limited the scope of the final supplemental EIS by failing to consider the cumulative effects of all three dam projects. Lost Creek Dam, Applegate Dam, and Elk Creek Dam, the first two of which already have been completed. The Resources Council contends that the Corps should address the cumulative effects of the dams in a single EIS because the three components of the Rogue River Basin Project are connected.[9]
The "cumulative impact" regulation requires the Corps to evaluate "the incremental impact of the action when added to other past, present, and reasonably foreseeable actions." 40 C.F.R. § 1508.7. Although the CEQ guidelines require that "cumulative actions" be considered together in a single EIS, 40 C.F.R. § 1508.25(a)(2), and "cumulative actions" consist only of "proposed actions," this does not negate the requirement of 40 C.F.R. § 1508.7 that the Corps consider cumulative impacts of the proposed actions which supplement or aggravate the impacts of past, present, and reasonably foreseeable actions.
The district court correctly ruled that a separate EIS was not required for the entire project. Only proposed actions must be discussed in a separate EIS. 40 C.F.R. § 1508.25(a)(2). The court also concluded that the final supplemental EIS adequately described and analyzed theimpacts in terms of the effects of the entire project. The court was convinced that the Corps took a hard look at the cumulative impacts in the EIS.
We disagree with the district court that the Corps took a hard look at the cumulative environmental impacts. Plaintiffs point out two examples of the Corps' failure to consider the cumulative impacts. First, although the final supplemental EIS conceded that the overall basin project would increase the turbidity of the Rogue River, it concluded that there would be no major adverse effect on fish production from increased turbidity. In reaching this conclusion, however, it considered only the turbidity created by the individual project. Similarly, in response to a comment made by the United States Environmental Protection Agency suggesting that the EIS should discuss the effects of Lost Creek Dam on downstream water quality, the Corps responded that the Elk Creek EIS was not the proper place to discuss the effects of Lost Creek Lake. Insofar as the effects of the Lost Creek Dam were necessary to a complete presentation of the cumulative impact of construction of Elk Creek Dam, we disagree.
The synergistic impact of the project should be taken into account at some stage, and certainly before the last dam is completed. In Kleppe v. Sierra Club, 427 U.S. 390 (1976), the Court specifically noted that "an agency could approve one pending project that is fully covered by an impact statement, then take into consideration the environmental effects of that existing project when preparing the comprehensive statement on the cumulative impact of the remaining proposals." Id. at 415 n.26.
While a separate EIS is not required, the Corps should consider the impact of Elk Creek Dam in conjunction with Lost Creek Dam and, if appropriate, Applegate River Dam. The Corps is building Elk Creek Dam in an area that already has two dams. It must consider the area as it finds it and take into consideration the cumulative impact of the basin project.
VI.
We affirm the district court's rulings on the Resources Council's remaining three challenges. First, the Resources Council contends that the final supplemental EIS gave no meaningful response to comments critical of the Corps' draft supplemental EIS, because these comments were not integrated into the body of the final supplemental EIS. The Resources Council relies on a CEQ regulation that requires discussion "at appropriate points in the final [EIS of] any responsible opposing view." 40 C.F.R. § 1502.9(b). The Resources Council argues that the only "appropriate points" in an EIS for discussion of opposing views are in the body.
We first note that section 1502.9(b) does not define "appropriate points."[10] We must therefore examine that guideline and the Corps' final supplemental EIS in light of the purposes of an environmental impact statement of providing complete information to the decisionmaker and the public.
[18 ELR 20326]
We find that an agency may place responsible opposing views in a separate "comments and responses" section when, as here, many of the critical comments prompted revisions in the body, the Corps discussed in the body all of the environmental problems to which the comments were addressed, and the Corps provided thoughtful and well-reasoned responses to most of the critical comments. We therefore hold that the Corps sufficiently complied with the purposes of the NEPA in its treatment of opposing views, even if the most "appropriate points" for addressing those views would be in the body.[11]
Second, the Resources Council contends that the final supplemental EIS is inadequate because it fails to discuss, as required by 40 C.F.R. § 1502.16(c), possible conflicts between the proposed action and other federal policy objectives for the affected area. Specifically, the Resources Council argues that the agency failed to analyze the effect of the dam on the wild and scenic portion of the Rogue River, located fifty-seven miles downstream. An EIS need contain only a reasonably thorough discussion of the significant aspects of the probable environmental consequences of a proposed action. Trout Unlimited v. Morton, 509 F.2d 1276, 1283 (9th Cir. 1974)).
In this case, the United States Forest Service commented that the final supplemental EIS should address the effect of the project on the wild and scenic portion of the river. The Corps responded that, based on its conclusion that the impact on the immediate downstream portion of the river would be insignificant, the impact on the wild and scenic portion fifty-seven miles downstream also would be insignificant. The agency assumed that the reservoirs' impacts diminish with distance.
Applying this court's "rule of reason," see Enos, 769 F.2d at 1372, the agency logically concluded that the impact from the project on the wild and scenic portion of the river would be insignificant.[12] Assuming the agency reaches the same conclusion concerning the immediate downstream portion of the river after it takes into consideration the new information, its decision concerning the wild and scenic portion of the river will stand.
Third, the Resources Council contends that the final supplemental EIS is defective because the Corps placed a cost-benefit analysis of the Elk Creek Project using a 3 1/4% discount rate in the body, but relegated an analysis based on a more realistic 7 1/2% rate to an appendix. The Resources Council argues that the placement of these analysis misled the decisionmaker as to the economic value of the project.
An EIS is not required to contain a formal, mathematically expressed cost-benefit analysis. California v. Block, 690 F.2d at 764. Nevertheless, if such an analysis is included, it should not be misleading. See Johnston v. Davis, 698 F.2d 1088, 1094 (10th Cir. 1983).
We find that the Corps' use of a 3 1/4% discount rate or its placement of the 7 1/2% cost-benefit analysis in an appendix was not misleading. The Water Resources Development Act of 1974, Pub. L. No. 93-251, § 80, 88 Stat. 34 (1974) (codified at 42 U.S.C. § 1962d-17(b)), required use of the 3 1/4% discount rate. Johnston, 698 F.2d at 1092-95. The Corps' inclusion of the analysis based on the more realistic 7 1/2% comported with CEQ guidelines. See 40 C.F.R. § 1502.23 (cost-benefit analysis "shall be incorporated by reference or appended to the statement"). Moreover, although the purposes of an EIS might have been better served if the 3 1/4% analysis in the body had made reference to the 7 1/2% analysis in the appendix, the inclusion of the latter analysis sufficiently cured whatever misleading effects resulted from use of the 3 1/4 percent rate. Cf. Enos, 769 F.2d at 1375 n.14.
VII.
We conclude that the Corps' mitigation report is inadequate, and that the Corps should file a new supplemental EIS because of new information obtained. The Corps also must prepare a worst case analysis or conduct further research with regard to the waterflow contribution from Elk Creek. The Corps also should conduct a worst case analysis based on the new information submitted in the two studies, if necessary. Finally, although the Corps need not prepare a separate statement addressing the cumulative impact of the dams, it should supplement the statement and address the cumulative impact of Lost Creek and Elk Creek Dams and, if appropriate, Applegate River Dam. We therefore remand to the district court for entry of appropriate injunctive relief in accordance with this opinion.
AFFIRMED IN PART, REVERSED IN PART, AND REMANDED.
1. "Turbidity" is defined in the glossary to the final supplemental EIS as "an expression of the optical property of water which causes light to be scattered and absorbed rather than transmitted through in straight lines. Turbidity is caused by the presence of suspended matter." Simply stated, turbidity is murkiness due to stirred-up sediment.
2. The plaintiffs are several nonprofit organizations representing their members who assert injury by the dam's construction. The plaintiffs therefore have standing under the rule in Sierra Club v. Morton, 405 U.S. 727, 735 (1972).
3. We note, however, that the factors set forth in Stop H-3 Ass'n v. Dole, 740 F.2d 1442, 1464 (9th Cir. 1984), cert. denied. 471 U.S. 1108 (1985), to determine reasonableness are neither mandatory nor exclusive. Warm Springs Dam Task Force v. Gribble, 621 F.2d 1017 (9th Cir. 1980), upon which Stop H-3 Ass'n relies, specifically states that "[r]easonableness depends on such factors as . . . ." Id. at 1024 (emphasis added).
4. The district court noted that the Corps is still reviewing the concerns expressed in the final Department study. Because the Corps has yet to complete its review of the new information, it is too early to conclude that the new information is not significant.
5. An epizootic disease is a disease that affects many members of a population at the same time. See Webster's Third New International Dictionary 766 (1976).
6. The WESTEX model is a mathematical model developed by the Corps' Waterways Experiment Station in Vicksburg, Mississippi, and the University of Texas. The Corps used this model to analyze potential turbidity problems from Elk Creek Dam.
7. We note that the United States Fish and Wildlife Service also recommended a new supplemental EIS because there may no longer be a need for the water storage assumed necessary in the final supplemental EIS.
8. We reject the argument of the Corps that section 1502.22 is inapplicable due to its rescission on May 27, 1986. The worst case regulation is a codification of prior NEPA case law. See Save Our Ecosystems v. Clark, 747 F.2d 1240, 1244 (9th Cir. 1984). Thus, the rules embodied in the regulation remain in effect even though the regulation was rescinded.
9. The parties disagree as to the appropriate standard of review for this issue. The Resources Council contends that the decision to limit the scope of an EIS is akin to a decision not to prepare a statement at all. Therefore, under Foundation for N. Am. Wild Sheep v. United States Dep't of Agric., 681 F.2d 1172, 1177 (9th Cir. 1982), we would review the decision to determine its reasonableness. Appellees contend that this court should review the decision to determine whether it is arbitrary and capricious. Neither contention is correct. As stated previously, this court reviews the district court's conclusion to determine whether it is based on an erroneous legal standard or on clearly erroneous findings of fact. See Northwest Indian Cemetery Protective Ass'n, 795 F.2d at 696.
10. As originally drafted, section 1502.9(b) read: "In the final statement the agency shall discuss at appropriate points in the text the existence of any responsible opposing view . . . ." 43 Fed. Reg. 25,237 (1978). Because the deletion of the words "in the text" was not accompanied by an explanation, see 43 Fed. Reg. 55,995 (1978), it is unclear whether the CEQ intended the change to affect the meaning of "appropriate points."
11. Moreover, to the extent that the critical responses of the state and federal agencies were merely "substantive comments," rather than "responsible opposing views," the Corps was not required to discuss the comments in the text. See 40 C.F.R. § 1503.4(b).
12. The Resources Council contends that the agency's assumption violates 40 C.F.R. § 1502.24, which requires agencies to identify any methodologies used and to make explicit reference by footnote to the scientific and other sources relied on for conclusions in the statement. We disagree. The regulation is satisfied here because the Corps identified the methodologies used and sources relied on for its conclusions concerning the immediate down-stream portion of the stream. This was sufficient to support its decision concerning the wild and scenic portion of the river.
[18 ELR 20326]
WALLACE, Circuit Judge, concurring in part and dissenting in part:
I concur in parts II and V of the majority opinion. I concur in part IV except for the statement in the final paragraph that the Corps must consider the "new information" provided by the reports discussed in part III in reaching its decision concerning a worst case analysis. With respect to part VI, I concur in the result only because some unnecessary language keeps me from fully joining that part of the opinion. I dissent from part III.
I
I am unable to agree with the majority's conclusion in part III regarding the need for a new supplemental environmental impact statement (EIS). As the majority points out, we will uphold an agency's decision not to supplement an EIS in light of new information if the decision is reasonable. Enos v. Marsh, 769 F.2d 1363, 1373 (9th Cir. 1985). As the majority also observes, reasonableness depends on four factors: "[1] the environmental significance of the new information, [2] the probable accuracy of the information, [3] the degree of care with which the agency considered the information and evaluated its impact, and [4] the degree to which the agency supported its decision not to supplement with a statement of explanation or additional data." Stop H-3 Association v. Dole, 740 F.2d 1442, 1464 (9th Cir. 1984) (Stop H-3), cert. denied, 471 U.S. 1108 (1985). I believe that the proper application of each of the four factors, as mandated by Stop H-3, to the two studies cited by the majority leads to the conclusion that the Corps' decision was reasonable. I will treat each of the two studies separately.
[18 ELR 20327]
A.
The first study was performed by the Oregon Department of Fish & Wildlife (Department). It argued that the construction of the dam would increase turbidity, water temperature, and the prevalence of epizootic diseases, with deleterious effects on the fish population in the Rogue River. I agree that the data provided in the Department's report, if accurate, are significant. I question, however, the report's accuracy.
In order to apply the four Stop H-3 factors, we must first examine the relevant evidence in the administrative record. The Corps had the report examined by two independent experts. One of these experts, a professor at the University of Washington School of Fisheries, filed an extensive and highly critical review of the report. Though this review admitted that some of the conclusions in the Department's study were valid, it also indicated that the study contained "considerable statistical inaccuracies, over-extension of statistical methods, and undue biological speculation"; reported that other conclusions of the study, though apparently valid as far as they went, were not statistically significant; disagreed with some of the study's interpretations of causation; questioned the strength of the study's data and the accuracy of the models it used in reaching its conclusions; dismissed some statements from the report as "spurious" and others as "speculation . . . [that was] unfounded"; and accused the authors of the study of throwing out data that did not fit their conclusions.
The second independent expert to evaluate the study was less negative in his assessment. He stated that the study's base methodology of comparing pre- and post-dam conditions was "not likely to yield conclusive results" and that the Department's model was based on "limited data over only a few years," which substantially increased the likelihood of "chance relationships." He also pointed out internal contradictions in the report.
The Corps' own expert at the Waterways Experimental Station in Vicksburg, Mississippi, observed that the study's authors had admitted that they had worked with very limited data and "were stretching" their methodology and that their report, therefore, was likely to contain some inaccurate conclusions. These shortcomings, the Vicksburg report stated "must be considered when assessing the predictive value of the information provided by the [Department]." The Corps' expert also said that the report's conclusions were based upon an insufficient number of observations and that the report treated dependent variables inconsistently.
Deposition testimony in this case presents a similar picture. Steven Cramer, the Department's program leader for the Rogue Basin Evaluation project, testified that, despite attempts at testing, the Department had been unable to confirm that the Lost Creek dam, which had served as a basis for the Department's comparison of pre- and post-dam conditions, was responsible for the increase in epizootics that had led to rises in fish mortality there. Cramer also admitted that the Department had not adequately tested the possibility that diseased hatchery fish, not dam construction, might have been what transmitted epizootics to the wild chinook salmon.
Cramer also admitted that there had been no unusual fish mortality since 1981, and that his calculations on fry survivability might be "inaccurate." He had earlier revised his estimates on fry mortality due to temperature increases from the 60-80% to the 35-40% range. He also conceded that his calculations ignored the probable beneficial effect that the proposed dam's regulation of peak flows would have on fry survivability. Indeed, the Department had previously admitted that the dam would probably also have beneficial effects that would reduce fry mortality.
Furthermore, the Department's District Fish Biologist for the Upper Rogue Basin testified that temperature increases were "at this time . . . not as much of a concern" as before, since proper reservoir management could obviate problems. Apparently, water temperatures would increase enough to endanger fry hatching only if a high volume of water were released.
There is also evidence that the Corps sought to respond to most of the Department's concerns about the construction of the proposed dam. On October 11, 1983, the Corps issued a written response to questions raised by various groups regarding the dam which explicitly addressed the Department's concern over increased turbidity, indicating that proper dam management would minimize increases in turbidity in the Rogue. In addition, Corps' analyst Dortch indicated that he had applied accurate models and found that the dam would have little effect on temperatures in the Rogue River because Elk Creek contributed only a small proportion of the Rogue's water. It is not clear, however, whether the Corps ever transmitted the results of this study to the Department. There is also no evidence that the Corps responded in any way to the Department's concern regarding increases in epizootics.
On the basis of this evidentiary background, we can apply the four factors delineated in Stop H-3 to determine the reasonableness of the agency's decision not to issue a supplemental EIS. The first factor is the "environmental significance" of the new data at issue. The data provided in the Department's study, if accurate, would indeed be significant. The second factor is the "probable accuracy of the information." Stop H-3, 740 F.2d at 1464. As is evident from the foregoing, much of the information in the Department's study is of a highly questionable accuracy at best, and the Corps had good reason, based on its own analysis and that of two independent experts, to doubt the validity of the study's conclusions. Even the majority is forced to admit that the Department's evidence on fry survivability, turbidity, and epizootics was "not conclusive." Majority op. at 12. The third factor is the "degree of care with which the agency considered the information and evaluated its impact." Stop H-3, 740 F.2d at 1464. The Corps exercised a high degree of care in considering the Department study, submitting it for assessment and review not only to its own analyst, but to two outside experts as well. In addition, in response to the concerns that the Department had raised, the Corps also apparently tried to develop a new model to serve as a basis for assessing some of the environmental effects of the construction of the proposed dam, evidently with some success. Moreover, as the majority points out, the Corps is continuing to review the concerns raised in the Department's study. The fourth factor is the "degree to which the agency supported its decision not to supplement with a statement of explanation or additional data." Stop H-3, 740 F.2d at 1464. As outlined above, the Corps provided a formal response to the Department regarding one of the three major concerns raised in its study: increased turbidity. It also performed additional analytical testing to assess the damage of increased temperatures, though it evidently did not publish the results of this testing or transmit them to the Department, as the wording of the fourth factor in Stop H-3 would imply it should.
Considering all of these factors together, I cannot agree with the majority's conclusion that the Corps' decision not to issue a supplementary EIS in response to the Department's study is unreasonable. In view of the dubious nature of so [18 ELR 20328] many of the study's conclusions and the care with which the Corps examined the concerns raised in the study, its decision seems to me to have been reasonable.
B.
I am less confident that the United States Soil Conservation Service (Conservation Service) report is significant even if it is accurate. That report indicated the presence of much greater amounts of high sediment-producing type soils in the vicinity of the Elk Creek dam site than the Corps had estimated. However, the Corps' expert testified that the Conservation Service's study had been based on a completely different methodology and addressed different objectives than the Corps' own study. He claimed that the Corps' study had concentrated on predicting water-sediment levels rather than merely noting soil types and that the Corps had developed an experience-based model that predicted lower resultant turbidities than the mere examination of soil types might lead one to expect.
The area soils scientist of the United States Geological Survey testified that some 83% of the shore of the lake that the proposed Elk Creek dam would produce would be of a high sediment-producing type. Nevertheless, the experience-based model the Corps had applied to the Elk Creek site had also been applied to the existing Lost Creek dam area and had turned out actually to have over-predicted resultant turbidity there. The Corps contemplated depositing gravel on trouble areas on the shoreline of the future lake in order to halt erosion and further reduce expected resultant turbidity. The area soils scientist also testified that, in his opinion, the Corps had taken a "hard look" at the concerns he had raised regarding turbidity, even though he felt that the Corps' conclusions contained "small inaccuracies."
With respect to the first Stop H-3 factor, the Corps had good reason to question whether the Conservation Service's report was even significant, since the Corps had considerable empirical evidence that soil type and turbidity are not, in actuality, as directly related as the report assumed. As for the second Stop H-3 factor, the reports about soil type are apparently accurate, but this really matters very little if they are not accurate predictors of turbidity. Nor do I think that the application of the third prong of Stop H-3 supports a holding that the Corps acted unreasonably: the Corps apparently performed no new studies in response to the Conservation Service report, but the Corps did compare the Conservation Service study to the results produced by its own model which over-predicted turbidity rather than underpredicting it. The Corps seems to have had good reason to conclude that the concerns of the Conservation Service study were unfounded. As for the fourth Stop H-3 factor, there was, evidently, no direct response by the Corps to the Conservation Service. Considering all four factors together, I disagree with the majority's conclusion that the Corps' decision not to issue a supplemental EIS in response to the Conservation Service study was "unreasonable" in these circumstances.
It is not the function of this court to decide whether the Corps' analysis of the two studies was "correct" scientifically. Whether or not it was, the record certainly seems to show that the Corps' decision not to issue a supplemental EIS was reasonable according to the four factors that we must apply under the rule of Stop H-3.
II
In part VI, the majority chooses to tackle the issue of whether responses to critical comments need be integrated into the body of an EIS or can simply be put at the end. The relevant regulation requires that criticisms be addressed at "appropriate points in the final statement." 40 C.F.R. § 1502.9(b) (1986). As the majority points out, the proposed version of this regulation had required that responses be "in the text," but this phrase was amended. Majority op. at 14 n.7. I conclude, therefore, that both the plain language of the regulation and its "legislative" history clearly indicate that criticisms need only be addressed somewhere in the EIS.
The Resources Council's only contention is that putting responses to criticisms in a separate "comments and responses" section is automatically invalid. The regulation clearly indicates otherwise. That should end the issue. There is no need to look further, as the majority does, to determine in which cases a separate comments section might be an "appropriate point." The Resources Council does not contend that even if including responses in a separate comments section is valid as a general rule, it is not valid in this case because the responses were tucked away in an inappropriately obscure portion of the statement. Because the Resources Council has pointed to no violation of the regulation in this case, it seems inappropriate for us to develop a rule ("We find that an agency may place responsible opposing views . . .," majority op. at 18). The proper approach would also eliminate the necessity of trying to create a distinction between "substantive comments" and "responsible opposing views," as the majority is forced to do. Majority op. at 15-16 n.8.
18 ELR 20321 | Environmental Law Reporter | copyright © 1988 | All rights reserved
|