17 ELR 20018 | Environmental Law Reporter | copyright © 1987 | All rights reserved


Sierra Association for Environment v. Federal Energy Regulatory Commission

No. 85-7390 (791 F.2d 1403) (9th Cir. June 17, 1986)

The court holds that petitioner's failure to seek rehearing before the Federal Energy Regulatory Commission (FERC) within 30 days of FERC's order staying the effective date of a hydroelectric project license is a jurisdictional bar to judicial review of the order. The court observes that the Federal Power Act affords it jurisdiction to hear a challenge to FERC orders only if the petitioner sought rehearing before FERC within 30 days of the order and filed for judicial review within 60 days after FERC's final order on the rehearing application. The court holds that petitioner failed to file petitions for rehearing and for judicial review within the statutory deadlines. Petitioner's request to terminate the hydroelectric project license, filed nine months after FERC issued the stay, was not intended as a timely petition for rehearing of FERC's stay order. The request to terminate was a demand that FERC perform statutory duties, not a request to reconsider its stay order. Even if the Sierra Association for Environment could bootstrap its objections to the license to the applicant's timely petitions for rehearing and reconsideration of the stay order, petitioner never presented its specific arguments in an application for rehearing directed to FERC. The court holds that petitioner's timely petition for rehearing of FERC's February 1985 order denying petitioner's request to terminate the applicant's license is an improper collateral attack on the earlier stay order. The request to terminate the license, based upon the fact that construction did not begin by a specified deadline, cannot succeed unless the earlier order staying the effective date of the license is vacated. The Federal Power Act does not allow a timely petition for review to apply to another FERC order for which time limitations have run.

Counsel for Petitioner
Glenn M. Kottcamp
616 P St., Fresno CA 93721
(209) 264-5000

Counsel for Respondent
Joshua Z. Rokach
825 N. Capitol St. NE, Rm. 3345, Washington DC 20426
(202) 357-8233

Counsel for Intervenor
Christopher D. Williams
McCarty, Noone & Williams
Suite 3206, 490 L'Enfant Plaza East, Washington DC 20024
(202) 554-2955

Before Sneed and Poole, JJ.

[17 ELR 20018]

Anderson:

Sierra Association for Environment (SAFE) appeals three orders issued by the Federal Energy Regulatory Commission (FERC or Commission). SAFE requests this court to issue an order directing FERC to vacate its orders (1) staying the effective date of Kings River Conservation District's (KRCD) license to build a hydroelectric project; (2) denying SAFE's request to terminate KRCD's license and granting KRCD a two-year extension within which to commence construction; and (3) dismissing SAFE's request for a rehearing. SAFE further requests that this court direct FERC to issue a written order terminating KRCD's license for failure to commence construction within two years.

On April 21, 1986, this court filed an order dismissing this appeal for lack of jurisdiction over the petition for review; finding the Commission's stay and one-time extension to be lawful; and disallowing attorneys' fees. Sierra Association for Environment v. Federal Energy Regulatory Commission, No. 85-7390 (9th Cir. April 21, 1986). What follows is an opinion in support of that order.

I. FACTS

The resolution of the issues involved in this appeal requires us to examine the complicated procedural history that has delayed construction of the Dinkey Creek hydroelectric project for more than four years.

Nov. 28, 1978KRCD filed an application with FERC for
a License for Authorization to construct
the Dinkey Creek Hydroelectric Project
located in Fresno County, California.
March 9, 1979FERC issued a Notice of Application for
Major License.
Sept. 10, 1979FERC permitted SAFE to intervene.
March 22, 1982FERC issued its Order Issuing Major
License for the Dinkey Creek Project. This
license required that construction com-
mence on or before March 1, 1984.
April 15, 1982SAFE filed an application for rehearing
pursuant to 16 U.S.C. § 825 1(a).
May 17, 1982FERC issued an Order Granting Rehear-
ing for Purpose of Further Consideration.
Nov. 15, 1982FERC denied rehearing.
Jan. 14, 1983SAFE filed, in this court, a Petition for
Review of FERC's Order Issuing Major
License pursuant to 16 U.S.C. § 825 1(b).
SAFE's Petition for Review was denied by
this court. See Sierra Ass'n for Environ-
ment v. FERC, 744 F.2d 661 (9th Cir.
1984). SAFE's various petitions for rehear-
ing before this court were denied and the
opinion in Sierra Ass'n for Environment v.
FERC became final on Najuary 14, 1985.
Jan. 24, 1984KRCD applied to FERC for a Stay Pend-
ing Completion of Litigation asking FERC
to issue an order to maintain the status quo
consistent with its order in City of Seattle,
12 F.E.R.C. P61,010 (1980).
Feb. 27, 1984SAFE filed an objection to the issuance of
the stay.
March 1, 1984Construction was to have begun. It had
not. License was to have become effective.
April 20, 1984FERC issued an Order Staying Effective
Date of License, effective the date KRCD
filed its request for Stay (Jan. 24, 1984).
The stay was granted until completion of
judicial review and was to maintain the
status quo.
May 21, 1984KRCD filed a Request for Rehearing of
Order Staying Effective Date of License.
June 20, 1984FERC issued a Notice of Denial of Rehear-
ing by Operation of Law.
July 16, 1984KRCD filed with FERC a Petition for
Reconsideration of Order Staying Effec-
tive Date of License.
Sept. 10, 1984SAFE filed a Petition for Supplemental
EIS's and a Continuance of the Stay.
Sept. 25, 1984KRCD filed an answer and objected to
SAFE's petition and continuance on the
ground that FERC lacked jurisdiction to
grant the relief requested due to the pend-
ing Petition for Review in this court pursu-
ant to 16 U.S.C. § 825 1(b).
Jan. 11, 1985SAFE filed a motion requesting KRCD's
license be terminated due to KRCD's fail-
ure to commence construction within the
time specified in its license.
Jan. 15, 1985KRCD filed a Motion to Lift Stay, for
Extension of Time to Commence Con-
struction and Answer to SAFE's Request
to Terminate License.
Jan. 28, 1985SAFE filed a response to KRCD's motion.
Feb. 15, 1985FERC denied SAFE's request to terminate
license and granted KRCD's request for a
one-time, two-year extension within which
to commence construction. FERC held
that KRCD's July 16, 1984 request for
rehearing concerning FERC's stay order
was rendered moot by FERC granting the
request for extension. KRCD's motion for
extension was granted as appropriate in the
public interest pursuant to 16 U.S.C. § 806.
Mar. 15, 1985KRCD filed a Request for Rehearing
requesting modification of the Feb. 15,
1985 order urging FERC to add "substan-
tial grounds" to support FERC's decision
in the event SAFE sought judicial review.
March 18, 1985SAFE filed an Application for Rehearing.
April 3, 1985SAFE filed Supplemental Arguments.
April 15, 1985FERC granted rehearing for the purpose of
further consideration.
July 5, 1985FERC issued an order dismissing SAFE's
Application for Rehearing and granting
KRCD's motion for rehearing for the lim-
ited purpose of modifying FERC's order of
Feb. 15, 1985 and granting KRCD the one-
time extension of time within which to
commence construction. Dismissal of
SAFE's rehearing petition was made on
grounds that SAFE never sought rehearing
of the April 20, 1984 order.
July 12, 1985SAFE timely filed a Petition for Review
with this court seeking judicial review of
FERC's Orders of April 20, 1984 (stay
order), Feb. 15, 1985 (denying termination
of license and granting extension of time),
and July 5, 1985 (dismissing SAFE's
rehearing application).
[17 ELR 20019]

II. DISCUSSION

FERC argues that SAFE is barred from attacking the April 20, 1984 order staying the effective date of KRCD's license because SAFE failed to seek a rehearing before FERC within thirty days of that order. FERC contends that because the request for rehearing of the stay order is a jurisdictional prerequisite to judicial review, this court has no jurisdiction to entertain SAFE's petition for review. We agree.

There is a presumption that persons aggrieved by administrative action are afforded judicial review. Ruff v. Hodel, 770 F.2d 839, 840 (9th Cir. 1985). However, that presumption gives way when the statute being applied precludes such relief. Id. The pertinent statute dealing with review of FERC [17 ELR 20020] orders is 16 U.S.C. § 825 1.1 Under this statute, two events must occur before this court has jurisdiction to review a petition for review of an order issued by FERC. First, the party aggrieved by an order issued by FERC must seek a rehearing before FERC of that order within thirty days. Second, the aggrieved party must file a petition for review in this court within sixty days after the final order of FERC upon application for rehearing.

The case law in this and other circuits is in agreement. Under the Natural Gas Act,2 "an application for rehearing is a jurisdictional prerequisite to judicial review." Boston Gas Co. v. Federal Energy Regulatory Com'n, 575 F.2d 975, 977 (1st Cir. 1978). Furthermore, the time requirements of the statute are as much a part of the jurisdictional threshold as the mandate to file for a rehearing. Id. Under 16 U.S.C. § 825 1, the statute involved here, a court has no jurisdiction to consider an issue not urged in a rehearing application. Federal Power Commission v. Colorado Interstate Gas Co., 348 U.S. 492, 498-99 (1955); Dept. of First & Game of State of Cal. v. Federal Power Com'n, 359 F.2d 165, 168-69 (9th Cir.), cert. denied, 385 U.S. 932 (1966); Cincinnati Gas & Elec. Co. v. F.E.R.C., 724 F.2d 550, 553 (6th Cir. 1984). See also Tiger International, Inc. v. Civil Aeronautics Board, 554 F.2d 926, 931 n.11 (9th Cir.), cert. denied, 434 U.S. 975 (1977) (Time limitations for certiorari, appeal and review set out in statutes are uniformly regarded as jurisdictional).

It is clear from the record that SAFE failed to meet either of these jurisdictional prerequisites as to the April 20, 1984 stay order. SAFE did not seek a rehearing of the stay order within thirty days nor did SAFE petition this court for review within sixty days of a denial of the rehearing petition.

SAFE makes two arguments why, even though it failed to seek a timely rehearing of the stay order, this court still has jurisdiction to review its petition for review. First, SAFE argues that it should be allowed to bootstrap its objections to the stay order to KRCD's timely petitions for rehearing and reconsideration of the stay order. On May 21, 1984, KRCD filed with FERC a timely request for rehearing of the stay order, and on July 16, 1984, filed a request for reconsideration of that same order. On January 11, 1985, during the pendency of KRCD's request for reconsideration of the stay order, SAFE filed its request to terminate KRCD's license. Thus, SAFE argues, the stay order was still subject to modification and SAFE, therefore, timely and properly presented to FERC the issue of FERC's authority to issue the stay order.3

We decline to accept SAFE's invitation to interpret the request on January 11, 1985, to terminate KRCD's license as a timely petition for rehearing of the April 20, 1984 stay order. It was clearly not intended as such. The request to terminate was a demand that FERC fulfill its statutory duty as set forth in the Federal Power Act. It was not a request that FERC rehear and reconsider its position on the stay order.

Furthermore, 16 U.S.C. § 825 1 requires that no objection to an order of FERC may be considered on review unless the same objection was first specifically raised in an application for rehearing directed to FERC. 16 U.S.C. § 825 1(a) and (b); City of Vanceberg, Ky. v. F.E.R.C., 571 F.2d 630, 642 (D.C. Cir. 1977), cert. denied, 439 U.S. 818 (1978). "As the Supreme Court has stated, it is the purpose of this provision to give the Commission notice of its alleged errors so that it may have the opportunity to correct them." City of Vanceburg, 571 F.2d at 642 (citing Federal Power Commission v. Colorado Interstate Gas Co., 348 U.S. 492, 498 (1955)). KRCD's petitions for rehearing and reconsideration did not raise any objection to FERC's jurisdiction to issue a stay order. Therefore, even if SAFE were allowed to bootstrap its arguments to KRCD's timely petitions, the objections that SAFE has to the stay order have never been specifically raised in an application for rehearing directed to FERC.

The second argument SAFE makes in favor of the existence of jurisdiction is that SAFE did file a timely petition for rehearing of FERC's February 15, 1985 order denying its request to terminate KRCD's license and granting KRCD's request for a one-time, two-year extension within which to commence construction. This timely petition for rehearing, argues SAFE, give this court jurisdiction to review its petition for review. FERC contends, however, that SAFE's request, on January 11, 1985, that FERC terminate KRCD's license and SAFE's timely petition for a rehearing of FERC's denial of that request on February 15, 1985, is simply an impermissible collateral attack on the April 20, 1984 stay order. We agree. SAFE's request to terminate KRCD's license was based on the fact that construction had not yet begun on March 1, 1984 as required in the license. The request to terminate, however, must fail unless the April 20, 1984 order staying the effective date of the license is vacated. Therefore, any attempt to satisfy the jurisdictional prerequisites required by 16 U.S.C. § 825 1 through the timely request for rehearing of FERC's denial of SAFE's request to terminate KRCD's license is a collateral attack on the April 20, 1981 stay order. The language of 16 U.S.C. § 825 1 does not permit the intertwining of orders for review purposes, that is, using a timely petition to review an order for which the time limitations have run. See Tiger International, 554 F.2d at 931 (examining 49 U.S.C. § 1486(a) which is worded similarly and contains time limitations similar to 16 U.S.C. § 825 1). The statute speaks in terms of individual orders: "No proceeding to review any order . . . shall be brought . . . unless . . . application [is made] to the commission for a rehearing thereon." (Emphasis added). See id. Since SAFE failed to timely seek either rehearing or review of the April 20, 1984 stay order, it [17 ELR 20021] is precluded from doing so now under the guise of filing a request that FERC terminate KRCD's license and then timely requesting a rehearing of FERC's denial of that request. See Gas & Elec. Dept. of City of Holyoke, Mass. v. FERC, 629 F.2d 197, 204 (1st Cir. 1980).

For the foregoing reasons, we DISMISS this appeal for lack of jurisdiction over the petition to review.4

DISMISSED.

1. 16 U.S.C. § 825 1 (1982) provides:

(a) Any [party] aggrieved by an order issued by the Commission . . . may apply for a rehearing within thirty days after the issuance of such order . . . . No proceeding to review any order of the Commission shall be brought by any person unless such person shall have made application to the Commission for a rehearing thereon. Until the record in a proceeding shall have been filed in a court of appeals, . . . the Commission may at any time, upon reasonable notice and in such a manner as it shall deem proper, modify or set aside, in whole or in part, any finding or order made or issued by it . . . .

(b) Any party . . . aggrieved by an order issued by the Commission . . . may obtain a review of such order in [a court of appeals], by filing in such court, within sixty days after the order of the Commission upon the application for rehearing, a written petition praying that the order . . . be modified or set aside in whole or in part . . . . Upon the filing of such petition such court shall have jurisdiction, which upon the filing of the record with it shall be exclusive, to affirm, modify, or set aside such other in whole or in part. No objection to the order . . . shall be considered by the court unless such objection shall have been urged before the Commission in the application of rehearing unless there is reasonable ground for failure to do so.

2. The relevant provisions of the Federal Power Act and the Natural Gas Act "are in all material respects substantially identical." Arkansas Louisiana Gas Co. v. Hall, 453 U.S. 571, 577 n.7 (1981) (quoting Federal Power Commission v. Sierra Pacific Power Co., 350 U.S. 348, 353 (1956)). Therefore, precedents under the Natural Gas Act apply with equal force to cases brought under the Federal Power Act. Id.; Municipal Light Board, etc., Mass v. Federal Power Com'n, 450 F.2d 1341, 1347 (D.C. Cir. 1971), cert. denied, 405 U.S. 989 (1972).

3. In SAFE's request to terminate KRCD's license, SAFE specifically addresses the issue of the propriety of the stay order.

4. Within 14 days from the date of filing this opinion, petitioner may file points and authorities in support of the petition for rehearing field on May 6, 1986.


17 ELR 20018 | Environmental Law Reporter | copyright © 1987 | All rights reserved