16 ELR 20412 | Environmental Law Reporter | copyright © 1986 | All rights reserved


United Steelworkers of America, AFL-CIO-CLC v. Rubber Manufacturers Association

No. 84-5842 (D.C. Cir. February 25, 1986)

The court holds that mandamus compelling the Occupational Safety and Health Administration (OSHA) to adhere to an expedited timetable for issuing a workplace exposure standard for benzene is not appropriate prior to the conclusion of the rulemaking process. The court first declines to determine in advance that OSHA's estimated 14-month timetable constitutes unreasonable delay under the Administrative Procedure Act even though the anticipated date for promulgating the final rule is about two-and-one-half years after OSHA's original estimated date. Determining the appropriate standard will involve assessment of many factors and OSHA does not yet even have public comments. OSHA's timetable is not facially unreasonable, especially compared to petitioners' proposed 12-month schedule. The court also declines to punish OSHA for its past delays by imposing an accelerated timetable. Although the court recognizes the potential health risks at stake, it rules that the agency's issuance of a notice of proposed rulemaking has mooted petitioner's claims of unreasonable delay. Even if the delay was unreasonable, judicial imposition of an accelerated timetable may result in hasty drafting. Finally, the court refuses to retain jurisdiction or require periodic progress reports, although it does observe that if OSHA fails to follow its schedule, petitioners may renew their mandamus claim.

Counsel for Petitioners
George H. Cohen, Robert M. Weinberg, David C. Vladeck
Bredhoff & Kaiser
1000 Connecticut Ave. NW, Washington DC 20036
(202) 833-9340

Counsel for Respondent
Laura V. Fargas, Francis X. Lilly, Frank A. White
United States Department of Labor
200 Constitution Ave. NW, Washington DC 20210
(202) 655-4000

Counsel for Intervenors
Charles F. Lettow, Linda J. Soldo
Cleary, Gottlieb, Steen & Hamilton
1752 N St. NW, Washington DC 20036
(202) 728-2700

Before: SCALIA and STARR, Circuit Judges, and McGOWAN, Senior Circuit Judge.

[16 ELR 20412]

Per Curiam: Benzene is a clear, colorless, flammable liquid employed in various industrial processes. It is undisputed that benzene poses significant health risks. In 1971, the Occupational Safety and Health Administration (OSHA), acting pursuant to summary procedures contained in section 6(a) of the Occupational Safety and Health Act of 1970 ("the Act"), 29 U.S.C. § 655(a) (1982), adopted a "national consensus standard" of ten parts benzene per million parts of air (10 ppm), averaged over an eight-hour time period, as the federal standard for exposure to benzene in the workplace. See 29 C.F.R. § 1910.1000 (1985) (Table Z-2). This standard, which remains presently in effect, was not designed to protect workers against benzene's carcinogenic effects. Indeed, it was not until the mid-1970's that scientific evidence clearly established a link between benzene and cancer. In 1978, OSHA responded to this evidence by promulgating a new "permanent standard," reducing the allowable concentration of benzene to 1 ppm. 43 Fed. Reg. 59,181 (1978). That standard was issued pursuant to section 6(b)(5) of the Act, 29 U.S.C. § 665(b)(5), which requires notice-and-comment rulemaking procedures. The agency's action, however, was vacated by the United States Supreme Court by virtue of OSHA's failure to make sufficient factual findings. See Industrial Union Dep't v. American Petroleum Inst., 448 U.S. 607 (1980).

[16 ELR 20413]

On July 8, 1983, OSHA publicly announced its intention to undertake a new, expedited rulemaking on benzene. The agency envisioned producing a completed proposal by November 1983, holding hearings in February 1984, and promulgating a final rule in June 1984. 48 Fed. Reg. 31,412, 31,413 (1983). That schedule was never implemented; indeed, as of December 10, 1984, the agency had not even begun the statutory rulemaking process by issuing a notice of proposed rulemaking (NOPR). On that date, petitioners filed in this court a petition for a writ of mandamus, seeking to require OSHA (1) to issue a NOPR within 30 days of the court's decision, (2) to undertake rulemaking "on a priority, expedited basis," (3) to issue a permanent standard seven months after issuing the NOPR, and (4) to file progress reports every 60 days. Petition for Writ of Mandamus at 12, No. 84-5842 (D.C. Cir. Dec. 10, 1984). Oral argument was set for December 11, 1985.

On December 5, 1985, virtually on the eve of oral argument, the agency filed with the court a copy of a just-issued NOPR, which was subsequently published in the Federal Register on December 10, 1985. 50 Fed. Reg. 50,512 (1985). The NOPR stated that the agency expected to hold public hearings on the proposed rule between March 11 and April 8, 1986. Id. at 50,572. At oral argument, counsel for the respondent revealed, for the first time, that OSHA had developed a new schedule for completion of the rulemaking. Following oral argument, this court issued an order directing the agency to confirm that estimated timetable in writing.* Order of December 17, 1985, No. 84-5842. The timetable subsequently submitted by the agency is as follows:

Close of Comment on NOPR:June 10, 1986
Completion of Staff Analysis:November 10, 1986
Termination of Rulemaking
Proceedings:February 10, 1987
Although declining to commit itself firmly to this schedule, the agency indicated that its proposed timetable "represents a realistic estimate at this time for the issuance of a final determination in this rulemaking."

In response, petitions now urge the court to reject OSHA's proffered schedule and to compel the agency to issue a final benzene standard by July 15, 1986, or, in the alternative, within a year of publication of the NOPR (i.e., by December 10, 1986). Petitioners also request that the court retain jurisdiction and require periodic progress reports from the agency.

After analyzing the various post-argument submissions in this case, as well as the various merits briefs, we conclude that mandamus compelling the agency to adhere to a more expedited timetable would not be appropriate. We follow instead the approach adopted quite recently by the court in a similar case, Oil, Chemical & Atomic Workers Int'l v. Zegeer, 768 F.2d 1480 (D.C. Cir. 1985) ("Radon Daughters"). As in that case, we cannot say in advance that the amount of time the agency contemplates taking to reach a final determination will constitute "unreasonable delay" within the meaning of section 706(1) of the Administrative Procedure Act, 5 U.S.C. § 706(1) (1982). In reaching its determination, the agency must, of necessity, deal with a host of complex scientific and technical issues. OSHA obviously cannot know at present how many comments it will receive or the nature of those comments. Moreover, the 14-month time period contemplated by OSHA does not seem to us facially unreasonable; indeed, the "alternative" schedule advanced by petitioners calls for completion of the proceedings within a comparable period of 12 months.

In addition, we decline the invitation to "punish" OSHA for its past delay by imposing a mandatory, accelerated timetable. To be sure, we fully appreciate the seriousness of the health risks posed by benzene and the consequent need for prompt agency action. We do not, however, have occasion to decide whether the period of delay prior to the December 10, 1985 NOPR was unreasonable, inasmuch as the issuance of the NOPR itself has mooted petitioners' claims to the extent that they were based upon that delay. But even were we to conclude that that delay was unreasonable, judicial imposition of an overly hasty timetable at this stage would ill serve the public interest. The rule ultimately promulgated by the agency, not to mention the agency's rationale for the rule, must be constructed carefully and thoroughly if the agency's action is to pass judicial scrutiny this time around. Cf. International Union, supra.

We likewise fail to perceive and useful purpose in retaining jurisdiction or requiring periodic progress reports, as requested by petitioners. Consistent with Radon Daughters, however, we leave the courthouse door open to petitioners to renew their petition for mandamus if OSHA should "fail to act with appropriate diligence in following the estimates it has tendered to this court." 768 F.2d at 1488.

For the foregoing reasons,the petition is dismissed without prejudice.

It is so ordered.

* We wish to emphasize to the parties their obligation to provide to the court, at the earliest point possible, all relevant information. In a case such as this, involving allegedly unreasonably delayed agency action, the court must consider the agency's performance record and its proposed timetable for completing its work. In that context, the court considers the specifics of the agency's proposed timetable highly relevant information.


16 ELR 20412 | Environmental Law Reporter | copyright © 1986 | All rights reserved