Natural Resources Defense Council v. NRC

ELR Citation: 13 ELR 20238
Nos. No. 82-1962, 695 F.2d 623/18 ERC 1868/(D.C. Cir., 12/07/1982)

The court rules that the Nuclear Regulatory Commission (NRC) may not allow site preparation activities for the Clinch River Breeder Reactor prior to issuance of a construction permit unless it finds that exigent circumstances warrant the exemption. Following a sua sponte reconsideration of the case, the court first withdraws its opinion and order of December 2, 1982. The court then holds that the NRC is bound by its prior interpretation of its regulations that exemptions are available only under exigent circumstances. It remands the record to the agency either to make a finding of emergency conditions or to proceed with an adjudicatory construction permit hearing.

Counsel for Petitioners
Barbara A. Finamore
Natural Resources Defense Council, Inc.
1725 I St. NW, Washington DC 20006
(202) 223-8210

Eldon V.C. Greenberg
Tuttle & Taylor
Suite 805, 1901 L St. NW, Washington DC 20006
(202) 861-0666

S. Jacob Scherr
American Society of International Law
2223 Massachusetts Ave. NW, Washington DC 20008
(202) 265-4313

Counsel for Respondents
Sheldon L. Trubatch, Acting Ass't General Counsel; E. Leo Slaggie, Acting Solicitor
Nuclear Regulatory Commission, Washington DC 20555
(202) 634-3288

Raymond N. Zagone, Jacques B. Gelin, Edward J. Shawaker
Land and Natural Resources Division
Department of Justice, Washington DC 20530
(202) 633-2749

R. Tenney Johnson, General Counsel; Joseph DiStefano; Leon Silverstrom, Ass't General Counsel, International Development & Defense Programs
Department of Energy, Washington DC 20585
(202) 252-5281

Counsel for Intervenor Tennessee Valley Authority
James E. Fox
Office of the General Counsel
TVA, 400 W. Summit Hill Dr., Knoxville TN 37902
(615) 632-2241

Before: MacKINNON, MIKVA, and EDWARDS, Circuit Judges.