15 ELR 20612 | Environmental Law Reporter | copyright © 1985 | All rights reserved


Vine Street Concerned Citizens, Inc. v. Dole

No. 84-6310 (604 F. Supp. 509) (E.D. Pa. February 28, 1985)

The court denies a preliminary injunction against construction on the Vine Street Expressway while an administrative decision on whether to prepare a supplemental environmental impact statement (SEIS) on simultaneous construction is pending, because no irreparable harm is likely before that decision is made. The court notes that to secure a preliminary injunction the plaintiff must demonstrate probable success on the merits, irreparable harm, and the absence of overriding third-party interests. On the merits, defendants concede that the decision to simultaneously build a convention center nearby will require them to reevaluate and possibly supplement the Expressway EIS, and they plan to do so when a draft EIS for the center is available. The court holds that until this evaluation is completed, the issue of whether an SEIS is necessary is not ripe. The court also finds that the plaintiff failed to demonstrate that irreparable harm would result from pre-construction activities occurring before the defendant's decision on the need for a SEIS, since the alleged harms are economic rather than environmental, the substantive issues in the lawsuit will be decided prior to actual construction of the Expressway, and much of the construction will actually improve the environment. Finally, the court finds that an injunction would subject third persons to possible harm and is contrary to the public interest, given the beneficial effect of the Expressway on the community. However, due to the countervailing public interest in discovery of the effects of the convention center construction on the Expressway project, the court expedites the case on the merits to ensure the prompt determination of the need for a SEIS.

Counsel for Plaintiff
Harold R. Berk
3030 PSFS Bldg., Philadelphia PA 19107
(215) 925-2051

Counsel for Defendants
John M. Hrubovcak
Department of Transportation
Commonwealth of Pennsylvania
1200 Transportation & Safety Bldg., Harrisburg PA 17120
(717) 783-2516

Rachel Shao
U.S. Attorney's Office
3310 U.S. Courthouse, Independence Mall, West 601 Market St., Philadelphia PA 19106
(215) 597-9179

[15 ELR 20612]

SHAPIRO, District Judge.

Plaintiff in this matter sought injunctive relief under the National Environmental Policy Act ("NEPA"), 42 U.S.C. § 4321 et seq., to prevent proposed pre-construction and construction activities on the Vine Street Transportation Improvements Project (the "Vine Street Expressway" or "Expressway") until defendants have prepared an adequate Supplemental Environmental Impact Statement considering the impact of simultaneous construction of the Vine Street Expressway and the proposed Philadelphia Convention Center.

Plaintiff Vine Street Concerned Citizens, Inc. ("Concerned Citizens") is a Pennsylvania non-profit corporation; its members include businesses and residents in the vicinity of the proposed Expressway construction. Defendants are Elizabeth H. Dole, Secretary of Transportation of the United States and Thomas D. Larson, Secretary of Transportation of the Commonwealth of Pennsylvania. This Expressway project is to improve that portion of the Vine Street Expressway (I-676) in Philadelphia between 17th and 18th Streets on the west and the Benjamin Franklin Bridge on the east. The project also includes ramps interconnecting with local streets and with the Delaware Expressway (I-95). The total length of limited access highway involved is approximately 1.3 miles.

Following a hearing on February 7, 1985, this court denied injunctive relief for reasons stated from the bench but retained jurisdiction to consider the merits of this litigation on an expedited basis. This memorandum is an elaboration of the court's bench opinion.

In 1980, a joint federal, state and city task force was formed to develop alternatives for Vine Street.1 The task force determined that the originally proposed full-scale Expressway could not be achieved without unacceptable displacement of significant community displacement of significant community resources and that there should be further consideration of alternatives. Preparation of the Draft Environmental Impact Statement ("DEIS") considering numerous alternatives was completed in December, 1982. Following public hearings, evaluation of all comments received, and further review and analysis, a two-volume Final Environmental Impact Statement ("FEIS") was prepared and approved by the Federal Highway Administration ("FHWA") in September, 1983. The FEIS selected a scaled-down Expressway alternative2 as the basis for design and construction of the project. The FHWA record of decision accepting the final design of the scaled-down alternative was issued on March 6, 1984.

The Expressway construction is planned for completion under four construction contracts. According to the Affidavit of Vito Genua, Project Manager for the Pennsylvania Department of Transportation, the contracts contemplated for 1985 provide for pre-construction activities; building four noise walls near Chinatown, installing air conditioning and double glazing on the windows at Holy Redeemer Church and School and Roman Catholic High School, removing the Reading Railroad viaduct, building a pumping station at 10th and Vine Streets and modifying one at 22nd Street, building a retaining wall for the 13th Street bridge, building a temporary service road, and relocating some utilities. These pre-construction activities require termination of certain leases for parking lots adjacent to the proposed construction and demolition of some buildings. Work on the pre-construction phase is scheduled to commence in March, 1985, but delays in obtaining necessary federal funds may force at least some postponement.3

During the preparation of the Expressway Draft and Final Environment Impact [15 ELR 20613] Statements, the City of Philadelphia was contemplating the use of several sites for a Convention Center. On September 15, 1983, one week prior to FHWA's issuing the FEIS, the City's Convention Center Steering Committee recommended that the Reading Terminal be selected as the site for a new Convention Center. The FEIS's discussion of the proposed Convention Center is limited to the following paragraph:

Convention Center — Two sites are currently being considered by the City of Philadelphia for future consideration of a Convention Center in Center City. These sites, Franklintown (A) and Reading Terminal (B) are within the Vine Street study area. Selection of a site is expected in August, 1983, with construction completed in 1987.

FEIS, Volume 1, p. 75.

The Philadelphia City Council approved the Reading Terminal site on October 4, 1984, and the City is currently preparing a DEIS for the Convention Center. According to the Government's testimony at this court hearing, this DEIS should be ready for circulation and public comment by the end of February or beginning of March, 1985.

The crux of the controversy before us is whether the simultaneous construction of the Expressway and Convention Center so essentially and extensively impacts the affected environment that a supplement to the Expressway FEIS is required.4 The pertinent federal regulation states:

The DEIS or FEIS may be supplemented at any time. Supplements will be necessary when there have been significant changes in the proposed action, the affected environment, the anticipated impacts, or the proposed mitigation measures.

23 C.F.R. § 771.129 (1984). The Concerned Citizens contend that until a supplemental EIS is prepared, all pre-construction and construction activities must cease or members of the Concerned Citizens will suffer irreparable harm. But defendants argue that whether there has been significant change is not properly before the court at this time. Because the Convention Center DEIS is not yet complete, the FHWA has not been able to determine whether the Convention Center plans constitute a significant environmental change meriting a supplemental EIS. Defendants also contend that until FHWA makes this decision, there is no final agency action ripe for review and this case is therefore premature. Furthermore, defendants assert that plaintiffs have failed to establish any irreparable environmental harm that will result from the pre-construction activities about to begin.

It is well established that the party moving for a preliminary injunction has the burden of proof and must show (1) a reasonable probability of eventual success on the merits, and (2) that irreparable injury pendente lite will occur if relief is not granted. Additionally, the court should consider, wherever relevant, (3) the possibility of harm to others from the grant or denial of injunctive relief, and (4) the public interest. In re Arthur Treacher's Franchisee Litigation, 689 F.2d 1137 (3d Cir. 1982); Oburn v. Shapp, 521 F.2d 142 (3d Cir.1975). In balancing these competing concerns, the court must consider the extraordinary nature of injunctive relief:

[a]n injunction should issue only where the intervention of a court of equity is essential in order effectually to protect property rights against injuries otherwise irremediable. . . . The basis for injunctive relief in the federal courts has always been irreparable injury and the inadequacy of legal remedies.

Weinberger v. Romero-Barcelo, 456 U.S. 305, 311, 102 S. Ct. 1798, 1803, 72 L. Ed. 2d 91 (1982) (citations omitted).

It was conceded by Louis Papet, Division Administrator of the FHWA, that the decision to build a Convention Center at Reading Terminal is of sufficient import to require reevaluation of the Expressway FEIS to determine if a supplemental EIS is necessary under 23 C.F.R. § 771.129. But the Government concedes only that considerationof whether a supplement is necessary must be made, not that a supplement will be necessary.5 It would be inappropriate for the court to review that results of that reevaluation now when the record is not sufficiently ripe. Plaintiff cannot demonstrate a likelihood of success on the merits because the underlying agency decision which the Concerned Citizens seek to challenge has yet to be made.

A FHWA reevaluation decision is expected approximately one month after the FHWA receives the Convention Center DEIS. If it decides not to supplement the Expressway FEIS, plaintiff may then challenge this final administrative action. The duty of the court would then be to review the administrative record to determine if the agency complied with NEPA's procedural requirements and the agency's refusal to supplement was not substantively arbitrary or capricious. See Citizens to Preserve Overton Park, Inc. v. Volpe, 401 U.S. 402, 91 S. Ct. 814, 28 L. Ed. 2d 136 (1971), Township of Springfield v. Lewis, 702 F.2d 426, 437 (3d Cir.1983) ("an agency's determination not to [revise] an EIS must be reasonable under the circumstances." (citations omitted)). If the FHWA determines to supplement the FEIS, then the court might consider the timetable for such an undertaking and the effect, if any, on the timing of phases planned for the Expressway project.6 When any supplemental EIS has been completed, the court may review the administrative record to determine if NEPA's procedural requirements have been met and the decision was not substantively arbitrary or capricious.

Plaintiff's burden of demonstrating harm is exacting:

The key word in this consideration is irreparable. Mere injuries, however substantial, in terms of money, time and energy necessarily expended in the absence of a stay, are not enough.

Oburn v. Shapp, 521 F.2d 142, 151 (3d Cir.1975) (emphasis in original). Plaintiff has failed to demonstrate that irreparable harm would result from the continuation of pre-construction activities until the FHWA decides whether to prepare a supplemental EIS.

The Concerned Citizens' alleged injuries are economic rather than environmental. No irreparable damage to the environment will occur during 1985's pre-construction activities and the substantive issues presented by this lawsuit will be decided on the merits prior to next year's planned beginning of the actual construction of the Vine Street Expressway.

The state's termination of leases for advertising signs and parking lots, if wrongful, may be remedied by money damages at law. See Ezy Parks v. Larson, 499 Pa. 615, 454 A.2d 928 (1982) (holding that Commonwealth Court abused its discretion in exercising its equitable power to enjoin the Pennsylvania Department of Transportation from terminating leases). Demolition of vacant buildings owned by the state is not even harmful; in any event, there has been no showing of irreparable harm to anyone.

[15 ELR 20614]

plemental FEIS as to the Sicily Island Levee Project? We think not.

Under the regulations of the Council of Environmental Quality (CEQ), an agency is required to supplement an original EIS if: (1) the agency makes substantial changes in the proposed action that are relevant to environmental concerns; or (2) there are significant new circumstances or information relevant to environmental concerns. 40 C.F.R. § 1502.9(c)(i) and (ii). The United States Court of Appeals for the Seventh Circuit has recently decided a case involving the question whether new information was sufficiently significant so as to require the preparation of a supplemental EIS. See State of Wisconsin, et al v. Weinberger, 745 F.2d 412 (1984). There, plaintiffs sued the Department of Defense demanding the preparation of a supplemental statement in connection with Project ELF, an extremely low frequency submarine communications system developed by the Navy. EISs had been prepared in 1972, 1975 and 1977 for several different proposals under the project. The project was shelved in 1978. It was reactivated in December 1981. Despite the presence of new information regarding the harmful biological effects of extremely low frequency electromagnetic radiation, a supplemental EIS was not prepared.

The court had occasion to state the significant new information test of 40 C.F.R. § 1502.9(c) several times throughout its opinion in State of Wisconsin, et al, supra:

". . . an original EIS may become inadequate when during the life cycle of a project its scope changes in any substantial way or if new circumstances arise or new information becomes available about previously unsuspected environmental impacts." (at 416).

* * *

"Thus, it seems clear that the principal factor an agency should consider in exercising its discretion whether to supplement an existing EIS because of new information is the extent to which the new information presents a picture of the likely environmental consequences associated with the proposed action not envisioned by the original EIS . . . The issue is whether the subsequent information raises new concerns of sufficient gravity such that another, formal indepth look at the environmental consequences of the proposed action is necessary. The supplementation process is extensive and an agency's determination as to when one is or is not needed is entitled to some deference. We hold, therefore, that an agency cannot have acted arbitrarily or capriciously in deciding not to file a SEIS unless the new information provides a seriously different picture of the environmental landscape such that another hard look is necessary. [emphasis in original]. (at 418). "Our task is the limited one of determinating whether or not the new information presents a seriously different picture of the likely environmental consequences of the proposed action not adequately envisioned by the original EIS, such that the Navy's failure to act on it was arbitrary or capricious." (at 419-20).

"We are only to decide whether the evidence reveals that the new informationpresents a seriously different picture of the environmental impact of the proposed project from what was previously envisioned, such that the Navy acted arbitrarily or capriciously in deciding not to file a SEIS." (at 421).

An agency's decision of whether to supplement an initial EIS must be made in the light of a previous in-depth review of the likely consequences of the proposed action. No benefit it to be derived from taking another "hand look" if that view is taken from the same vantage point and overlooks the same environmental panorama. The decision in Avoyelles was not a "significant new circumstances or information" which required the preparation of an additional EIS. No new scientific or technical information was revealed which indicated that the project might have environmental effects which differed from those analyzed in the original EIS. Although the Corps did prepare an FEIS in 1981, this analysis was done solely to consider the mitigating impacts of the Tensas Wildlife Refuge. We conclude that the Corps was not obligated to prepare a supplemental FEIS now.40

CONCLUSION

For reasons here stated, we decide that plaintiffs' request that the Corps re-open the Sicily Island EIS process is not warranted. We dissolve the temporary restraining order which has been in effect since the commencement of this action. We dismiss plaintiffs' complaint as failing to demonstrate in any manner that the Corps' decision to issue the 404 permits was arbitrary, capricious or an abuse of discretion.

THUS DONE AND SIGNED in Chambers at Lake Charles, Louisiana, on this the 20th day of September, 1984.

1. Planning for the Vine Street Expressway began during the 1960's and 1970's.

2. The scaled-down Expressway alternative is described in the FEIS as follows:

The four-lane Scaled-Down Expressway . . . separates through traffic from local directional service road traffic by extending the existing depressed lanes on Vine Street eastward from 17th Street to 9th Street, then becomes clevated to make direct connections to I-95 and the Benjamin Franklin Bridge. An interchange at 15th and 16th Streets will provide traffic movements between the local street system and the depressed expressway lanes. Ninth Street, Ridge Avenue, and Wood Street will be closed to through traffic. 5th Street will remain open at its intersection with the bridge approach.East of the 15th/16th Street interchange, eastbound expressway traffic exits at 8th Street. Entrance to the expressway westbound will also be provided at 8th Street. Local and CBD access to I-95 will be provided at Broad and 7th Streets. The intersection at 6th Street will be grade separated, for the westbound movement between the expressway and the Benjamin Franklin Bridge. The Benjamin Franklin Bridge Monument will be retained. The anticipated duration of construction is a 36-month period beginning in late 1985, with a total project cost of approximately 176 million dollars.

FEIS, Volume 1, p. 26.

3. According to Edward S. G. Dennis, Jr., United States Attorney for the Eastern District of Pennsylvania, funding considerations would not affect at least lease termination and building demolition.

4. Plaintiff's motion also appears to challenge the adequacy of the FEIS's consideration of construction impact on archeological resources and the need for alternative planning for a decking above the Expressway to permit continued northern development of Chinatown. However, since plaintiffs presented no argument or evidence that the FEIS failed fully to consider the decking alternative or that the archeological reports and studies were deficient, this court must assume that plaintiff chose not to pursue these contentions.

5. Such a reevaluation was made to determine if a proposed parking garage, located immediately adjacent to the project between 15th and 16th Streets, would result in any significant changes in the impacts identified in the FEIS. The reevaluation concluded that the garage would cause no significant changes in impacts over those discussed in the FEIS, so no supplemental EIS was prepared.

6. The proposed Convention Center could undergo many changes between its draft and final EIS.Any Expressway supplemental EIS would consider the likely impact only of those alternative Convention Center plans being given serious consideration at the time of preparation of the Convention Center DEIS.

40. As one court succinctly stated, "NEPA's rule of reason does not require rethinking of everything all the time." Ventling v. Bergland, 479 F. Supp. 174, 179 (D.S.D.1979), quoting Sierra Club v. Andrus, 581 F.2d 895, 906 (D.C.Cir.1978). The Supreme Court has noted: "Administrative consideration of evidence . . . always creates a gap between the time the record is closed and the time the administrative decision is promulgated . . ." Vermont Yankee Nuclear Power Corp. v. NRDC, 435 U.S. 519, 554-555, 98 S. Ct. 1197, 1217, 55 L. Ed. 2d 460 (1978); accord, Piedmont Heights Civic Club, Inc. v. Moreland, 637 F.2d 430, 442 (5th Cir.1981).


15 ELR 20612 | Environmental Law Reporter | copyright © 1985 | All rights reserved