Consolidated Edison Co. of N.Y. v. Kretchmer

Citation: 2 ELR 20125
68 Misc. 2d 545/3 ERC 1621/327 N.Y.S.2d 375, (N.Y. Sup. Ct., 12/23/1971)

Environmental Protection Administrator's decision not to permit a six month variance from requirements of the New York City Air Pollution Control Code for plaintiff's Arthur Kill generating station was preceded by a quasi-judicial hearing. Therefore, under CPLR 7803(4), judicial review jurisdiction lies in the Appellate Division and the administrator's decision must be affirmed if supported by substantial evidence.

Counsel for Plaintiff
Williams & O'Neill
130 East 15th Street
New York, New York

Counsel for Defendant
J. Lee Rankin
Corporation Counsel
Municipal Building
New York, New York